BacTech Environmental Corporation (CSE: BAC | OTCQB: BCCEF) has signed a Technical Consulting and Testing Agreement with Kazakhstan-based Di-As Company Ltd. to evaluate its proprietary BACOX® bioleaching technology on historic sulphide tailings in the Zyryanovsk district of East Kazakhstan. The Di-As-funded, three-stage program carries an estimated value of US$350,000 to US$425,000 and is expected to take approximately 26 to 34 weeks. The announcement is notable as it represents BacTech's first agreement structured to lead with BACOX®, with its developing Zero Tailings™ technology potentially to follow. Investors may be watching for results from each stage before any further development commitment is made.
Key Points
- BacTech Environmental Corporation (CSE: BAC | OTCQB: BCCEF) signed a Technical Consulting and Testing Agreement with Di-As Company Ltd.
- The agreement targets historic sulphide tailings at the Staroe facility in East Kazakhstan for BACOX® bioleaching evaluation
- The Di-As-funded program is valued at US$350,000 to US$425,000 and is expected to span approximately 26 to 34 weeks across three stages
- Investors should watch for Stage 1 and Stage 2 metallurgical results before any construction or commercial decision is considered
Staroe Tailings Facility and the Historical Estimate Behind the Di-As Decision
The Staroe tailings facility received material from former Zyryanovsk processing operations between 1953 and 1968. A protocol of the State Reserves Committee of the Republic of Kazakhstan, dated January 2, 2022, records 36.57 million tonnes grading an average of 1.16 grams per tonne gold and 6.62 grams per tonne silver, along with zinc, lead, and copper. BacTech explicitly cautions that this is a historical estimate only, not a current mineral resource or mineral reserve under National Instrument 43-101, and the company has not independently verified the historical tonnage, grades, or supporting data. The estimate is cited solely as the basis on which Di-As decided to fund a technical evaluation.
How the Three-Stage BACOX® Program Is Structured
The program proceeds in three stages, with technical results reviewed before each successive phase is committed. Stage 1 covers site assessment and diagnostic testing to determine how much gold is associated with sulphide minerals. Stage 2 involves bench-scale BACOX® amenability testing at ALS Laboratories in Perth, Western Australia, comparing gold and silver recovery against direct cyanidation and examining arsenic stabilisation. Stage 3, subject to positive earlier results, will produce preliminary engineering and costing for a nominal 50-tonne-per-day BACOX® circuit, with a possible modular pathway to approximately 100 tonnes per day. BacTech states Stage 3 is not a Preliminary Economic Assessment under National Instrument 43-101.
Agreement Effectiveness, Zero Tailings™ Optionality, and Commercial Pathway
The agreement becomes effective 30 days following formal commissioning of Di-As's new carbon-in-leach processing plant in Altay City and contains an 18-month longstop date. If technical results are positive, the parties may consider a future commercial arrangement for BACOX® deployment. The release also notes that BacTech and Di-As may consider whether Zero Tailings™ technology could have future application at the site, though the company states it is not part of the current program and its suitability for this material has not yet been established. No construction decision has been made, and no assurance of program completion or metal production is given.