Cabral Gold Inc. (TSXV: CBR) (OTCQX: CBGZF) has announced a series of major milestones at its Phase 1 gold-in-oxide heap leach project in Brazil's Cuiú Cuiú Gold District, including receipt of the Operating Licence from the Pará State environmental authority SEMAS/PA. Mechanical assembly of the adsorption, desorption, and recovery leach processing plant is complete, and first gold production is now targeting September — approximately six weeks ahead of the original schedule. Commercial gold production remains planned for Q4 2026, with commissioning of the wet processing circuit actively underway.

Key Points

  • Cabral Gold Inc. (TSXV: CBR) (OTCQX: CBGZF) operates the Cuiú Cuiú Gold District in Pará State, northern Brazil
  • Operating Licence received from SEMAS/PA; mechanical assembly of the ADR plant is complete; mining and stacking of oxide ore is in progress
  • First gold production targeting September, six weeks ahead of schedule; commercial production ramp-up planned for Q4 2026
  • Investors may watch progress on wet-circuit commissioning and the transition to full commercial output

Operating Licence and Cyanide Approvals Unlock Key Production Steps at Cuiú Cuiú

The granting of the Operating Licence from SEMAS/PA is described in the release as a major milestone, providing regulatory consent for cyanide use in the leaching process. Final approval for cyanide purchase and transport was also received from Brazilian military authorities. The company states the licence will serve as the foundation for future licensing efforts to migrate to a Full Mining Licence during the 2026 calendar year, building on the Preliminary Licence granted earlier in the year. Mining of gold-in-oxide ore and stacking on the first heap leach pad is now in progress, with irrigation expected to commence within days of the announcement.

ADR Plant Assembly Complete as Wet-Circuit Commissioning Gets Underway

The ADR leach processing plant arrived on site in late July and mechanical assembly has been completed. Electrical installation and testing are over 90% complete, with Como Engineering engaged to manage commissioning and operator training. The wet-circuit commissioning — covering Carbon Adsorption columns, Desorption, and ultimately gold doré production — is being jointly managed by Cabral, Como Engineering, and Australian metallurgical consultants Strategic Metallurgy. The release states that expenditures and schedule continue to track in line with the Pre-Feasibility Study dated July 29, 2025. Heap leach pad number two is expected to be complete by end of August.

Workforce Safety Record and Local Employment at the Cuiú Cuiú Construction Site

A combined total of 592,380 hours have been worked by the Owners Team and contractors to date in 2026. The project recorded its first Lost Time Incident, a non-critical knee injury to an Owners Team member, producing a Lost Time Injury Rate of 0.34 per 200,000 hours worked. The company states the affected employee is recovering and continuing medical follow-up. A total of 312 employees and contractors are currently on site, all of whom are Brazilian nationals, with approximately 67% sourced from Pará State. President and CEO Alan Carter noted the company's commitment to safety despite a rapid development timeline and challenging weather conditions.