Forge Resources Corp. (CSE: FRG) (OTCQB: FRGGF) (FSE: 5YZ) has announced a significant underground development milestone at its fully permitted La Estrella coal project in Santander, Colombia. The company reports that the underground junction connecting the access ramp to the crosscut is now complete, and 15 metres of crosscut have been excavated on a direct heading toward the first of eight known coal seams. With approximately 25 metres of additional advance required before reaching that first seam, investors in this Canadian-listed junior are watching progress closely as the project moves toward its next operational threshold.

Key Points

  • Forge Resources Corp. (CSE: FRG) holds an 80% interest in Aion Mining Corp., which is developing the La Estrella coal project in Santander, Colombia
  • The underground junction is complete and the crosscut has advanced 15 metres toward La Estrella's first coal seam
  • Approximately 25 metres of additional crosscut advance are estimated before the first seam is encountered
  • Infrastructure upgrades including a power capacity increase from 60 kW to 175 kW and additional ventilation are being planned to sustain heading progress

Underground Junction Completed as Crosscut Profile Transitions to Streamlined Configuration

The ramp-to-crosscut junction at La Estrella has been fully completed, enabling uninterrupted advance directly toward the deposit's coal seams. Of the 15 metres excavated so far, 10 metres were developed on a 12.4 m² steel arch profile, with the remaining 5 metres excavated on a more compact 9.0 m² arch profile. The company states the smaller profile is improving excavation, loading, and muck handling efficiency — a practical operational adjustment that the release suggests will support faster heading advance as development continues deeper underground at the Santander site.

Eight Known Seams of Metallurgical and Thermal Coal Within Reach at La Estrella

La Estrella hosts eight identified seams containing both metallurgical and thermal coal, and the crosscut is now advancing on a straight line toward the shallowest of these targets. The company estimates the first seam will be intercepted after approximately 25 more metres of development. CEO PJ Murphy stated in the release that reaching this seam "will mark a pivotal milestone for Forge Resources and is a major step on La Estrella's path toward extraction and cash flow," underscoring the operational and financial significance the company attaches to this near-term underground objective.

Power and Ventilation Upgrades Planned to Sustain Advance Toward Coal Seams

To maintain heading momentum as the crosscut lengthens and coal seams are approached, Forge Resources is planning a coordinated infrastructure upgrade. An additional 30 HP explosion-proof axial fan is to be installed approximately 120 metres along the underground ramp, supplementing the existing surface fan to reinforce airflow to the working face. Separately, on-site electrical generation capacity is planned to increase from 60 kW to 175 kW to support the expanded ventilation system and additional equipment requirements associated with deeper underground operations.