New Found Gold Corp. (TSX: NFGC) (NYSE American: NFGC) has released a revised Preliminary Economic Assessment and updated mineral resource estimate for its 100%-owned Queensway Gold Project in Newfoundland and Labrador. The revised study more than doubles the project's after-tax NPV5% to $1.728 billion at a base-case gold price of US$3,600 per ounce, while the internal rate of return stands at 126% with a payback period of less than one year. The Measured and Indicated Mineral Resource increased 38% to 1.920 million ounces of gold, partly driven by the addition of the newly discovered Dropkick Zone. Investors may be watching these results closely as the company positions Queensway as a near-term Canadian gold production asset.

Key Points

  • New Found Gold Corp. (TSX: NFGC) (NYSE American: NFGC)
  • Revised PEA returns after-tax NPV5% of $1.728 billion and 126% IRR at US$3,600/oz gold, with cumulative after-tax cash flows of $2.551 billion over a 15-year mine life
  • Total gold production of 1.744 million ounces planned; initial capital of $149.8 million; first mineralized material delivery to Pine Cove mill targeted for Q4/27
  • Investors should watch progress on Phase 1 construction, the forthcoming NI 43-101 technical report, and ongoing infill drilling targeting inferred resource conversion

Queensway PEA Economics: NPV and IRR Signal Strong Project Returns

The revised PEA projects after-tax NPV5% of $1.728 billion at a base-case gold price of US$3,600 per ounce, rising to $2.225 billion at US$4,100 per ounce. The after-tax IRR is 125.8%, with a payback period of less than one year. The project envisions total gold sales of 1.706 million ounces, average annual production of 116,000 ounces, and peak annual production of 190,000 ounces in 2032. All-in sustaining costs are estimated at US$1,375 per ounce over the life of mine. Initial capital is $149.8 million, consistent with the prior PEA, while growth capital totals $832.1 million across Phases 2 and 3.

Three-Phase Development Plan and Path to First Production at Pine Cove

Queensway is structured as a three-phase operation combining open-pit and underground mining. Phase 1 targets processing of 700 tonnes per day at the company's existing Pine Cove mill beginning Q4/27, with high-grade material trucked 275 kilometres from the Queensway site. Phase 2 introduces an on-site Queensway Mill at 4,900 tonnes per day from 2031, incorporating dual processing circuits for high-grade and lower-grade material. Phase 3 expands the gravity-flotation circuit to 5,000 tonnes per day from 2033, bringing total on-site capacity to 7,000 tonnes per day. The mine plan extends to 2040, with stockpile processing continuing until 2042.

Queensway Mineral Resource Grows 38% With Dropkick Zone Addition

The updated MRE reports Measured and Indicated resources of 1.920 million ounces of gold at 2.19 grams per tonne, representing a 38% increase of 528,000 ounces compared with the prior estimate. Inferred resources stand at 606,000 ounces at 1.51 grams per tonne. The addition of the Dropkick Zone, which the company states remains open along strike and at depth, contributed to this growth. The release notes that only a portion of the 110-kilometre strike extent along two major fault zones has been evaluated, and the company is conducting infill drilling to convert inferred resources to indicated status.

Funding Position and 530 Newfoundland Jobs Underpin Project Confidence

The company states it is fully funded for initial capital expenditures, citing approximately $167 million in cash and cash equivalents as at September 30, 2026, a further $35 million debt facility, potential warrant proceeds expiring in 2027, and cash flow from its 100%-owned Hammerdown Gold Deposit through 2027. A $220 million finance package is also referenced in the release. The company anticipates Phase 1 cash flows will fund growth capital for Phases 2 and 3. The project is expected to create 530 direct jobs in central Newfoundland over the life of mine.