Key Highlights

  • Non-GAAP EPS was USD 0.53 against USD 0.50 a year earlier.
  • 2026 non-GAAP EPS guidance rose to USD 1.90 to USD 1.92, with 2027 initiated.
  • The 10-year capital plan grew by USD 4 billion to USD 70.7 billion through 2035.
  • Houston Electric submitted 14 gigawatts of large-load demand to ERCOT.

CenterPoint Energy (NYSE:CNP) reported third-quarter non-GAAP earnings of USD 0.53 a diluted share, up from USD 0.50 a year earlier, with net income of USD 331 million against USD 293 million. The Electric segment earned USD 362 million against USD 293 million, while Natural Gas earned USD 44 million against USD 71 million, and Corporate and Other lost USD 75 million against USD 71 million on USD 6 million of higher borrowing costs; nine-month net income reached USD 891 million against USD 788 million. Management raised 2026 non-GAAP EPS guidance to USD 1.90 to USD 1.92, citing year-to-date execution, and initiated 2027 guidance of USD 2.07 to USD 2.09, about 9% growth at the midpoint, with financing costs USD 0.04 a share unfavorable reflecting USD 3 billion of new debt net of maturities.

A Larger Capital Plan and Expanded Equity Funding

The 10-year capital plan rose USD 4 billion to USD 70.7 billion through 2035, with USD 1.5 billion of projects originally slated after 2030 moved into the first five years; management projects enterprise rate base growth above 14% annually through 2030 and sees at least USD 10 billion of further opportunity through 2035, having invested USD 4.1 billion in the first nine months. The equity financing guide rose USD 1.6 billion to USD 4.5 billion, with USD 500 million to USD 700 million of common equity planned for 2027, and the Ohio natural gas distribution sale closed October 1 for about USD 1.4 billion of proceeds; adjusted funds from operations to debt reached 13.7% on the Moody's method for the 12 months ended September 30, with a corporate alternative minimum tax refund adding 60 basis points to full-year 2026 credit metrics.

Houston Demand Growth and Regulatory Items

Houston Electric originally submitted about 14 gigawatts of demand into the ERCOT Batch Zero process, estimating 10 gigawatts of base load and about 2 gigawatts of studied load remain, with about 2 gigawatts of studied load withdrawn during the audit; industrial and commercial leasing in Houston rose more than 30% year over year, and customers provided about USD 290 million in contributions in aid of construction and about USD 600 million of financial security in the quarter, of which about USD 135 million was returned. Management identified USD 5.5 billion of transmission projects, about 85% on brownfield sites, and plans 765 kilovolt filings in the first half of 2027; in Indiana, 700 megawatts of existing capacity is available for large industrial customers, with potential to reach 1.4 gigawatts, and a pending settlement would remove 15 large and five medium temporary generation units from rates, reducing the revenue requirement by USD 112 million if approved. Tracking points ahead include ERCOT decisions on the 10 gigawatts of base load demand, the regulatory ruling on the USD 112 million revenue requirement reduction, progress on the 2027 equity issuance, and operations and maintenance expense against the 1% to 2% reduction goal.