Key Highlights
- Second quarter 2026 results are listed for October 26, 2026; no figures yet.
- Cash was CAD 40.2 million at March 31; refinery budget is USD 73 million.
- Funding: CAD 17.5 million from Invest Ontario and a CAD 20 million federal agreement.
- Select commissioning is planned for late 2026; commercial production targets late 2027.
A Preview, Not a Results Report
No second quarter figures were available at the time of writing, and the calendar gave no release time. Electra Battery Materials (NASDAQ:ELBM) is building a cobalt sulfate refinery at Temiskaming Shores, Ontario, aimed at supplying battery makers. Its shares trade on Nasdaq and the TSX Venture Exchange.
The most recent quarterly results reviewed, for the first quarter, showed cash of CAD 40.2 million, net proceeds of about USD 4.6 million from share issues at an average of USD 0.91, and an at-the-market program raised to USD 25 million. The release reviewed did not report a net loss. A published consensus loss of USD 0.03 per share is listed for the upcoming report.
Construction Milestones and Money
On August 26, 2026, the company said structural steel erection, concrete work, equipment installation and piping were under way. The schedule runs as follows: select commissioning in the fourth quarter of 2026, mechanical completion in the second quarter of 2027, full commissioning and ramp-up in the third quarter of 2027, and commercial production in the fourth quarter of 2027. About CAD 32 million of construction contracts had been awarded by May 2026. Directors approved a refinery construction budget of USD 73 million in the first quarter of 2026.
Funding support includes definitive agreements with Invest Ontario for CAD 17.5 million, finalized by August 26, 2026, and a CAD 20 million Strategic Response Fund agreement with the Government of Canada. That federal agreement is 25% non-repayable and up to 75% repayable, so most of it is a loan-like obligation rather than a grant. Select commissioning is only a first operating step, and mechanical completion is a separate later milestone, so the plan has several checkpoints where delays could appear.
Risks and Items to Track
A USD 73 million budget is large next to a published market value near USD 47.86 million, so more funding looks likely. Issuing shares through the at-the-market program dilutes existing holders. Cost overruns, slippage against the 2027 timeline, cobalt prices and customer offtake are the main risks, and the company has no refinery revenue yet.
Investors can watch the quarterly report for cash, the net loss and construction spending, plus any change to commissioning dates and any new government funding or equity raises. The budget is stated in US dollars while cash is reported in Canadian dollars, so currency moves also change how much of the cost current cash covers.
Where the Project Stands
Construction is moving, but the refinery is not yet producing. Select commissioning is planned for late 2026 and commercial production for the fourth quarter of 2027. Cash of CAD 40.2 million at March 31 and government support underpin the build, yet the budget relative to market value points to further capital needs. The quarterly report should show how much cash has been spent, and construction timelines often shift.