- TSXV:KRY gained 6.67%, with the latest rally coming after a series of strong drill results from the Haib Copper Project in southern Namibia.
- The August 26 drilling update delivered the longest continuously mineralized intersection drilled at Haib to date: 969 metres at 0.27% CuEq.
- Another hole returned 413 metres at 0.41% CuEq, including 236 metres at 0.57% CuEq.
- Haib's March 2026 resource estimate contains approximately 2.09 million tonnes of contained copper in the indicated category and 1.39 million tonnes inferred, alongside significant molybdenum and gold.
- Koryx is targeting publication of a Pre-Feasibility Study before the end of 2026, making the next few months particularly important for the stock.
Why Is Koryx Copper Stock Rising 6.67%?
The latest 6.67% gain in TSXV:KRY comes against a backdrop of increasingly positive exploration and development news from Haib.
Koryx is progressing Haib from a large exploration and resource story toward a more advanced development proposition. The latest drilling continues to demonstrate the project's exceptional scale and continuity, while technical work is being incorporated into the upcoming PFS.
For investors, the combination of a large copper resource, long mineralized intervals, improving project design and a defined PFS timeline is creating a stronger potential re-rating narrative.
Haib Delivers Exceptional Drill Continuity
The biggest recent catalyst is the August 26 drilling announcement.
Koryx reported results from 19 holes totalling more than 8,586 metres. All 19 holes intersected thick mineralization, with multiple intervals above the average resource grade.
The standout result was hole HM167, which returned:
969 metres at 0.27% CuEq from surface
The interval included higher-grade sections of 18 metres at 0.48% CuEq, 58 metres at 0.45% CuEq and 28 metres at 0.42% CuEq.
Another major result, HM185, returned 413 metres at 0.41% CuEq, including 236 metres at 0.57% CuEq.
HM177 delivered 413 metres at 0.38% CuEq, including a near-surface 30-metre interval grading 1.10% CuEq.
These results are important because Haib is a very large porphyry system where scale, continuity and predictable mineralization are critical factors in determining potential mine economics.
Updated Resource Gives Haib Significant Scale
Koryx's March 2026 resource estimate further strengthened the project's Investment proposition.
Haib contains approximately 744 million tonnes grading 0.28% copper in the indicated category, representing about 2.09 million tonnes of contained copper. The inferred category adds approximately 579 million tonnes grading 0.24% copper, or about 1.39 million tonnes of contained copper.
The resource also includes approximately 103.6 million pounds of contained molybdenum in the indicated category and 84.5 million pounds inferred, plus substantial gold credits.
The inclusion of molybdenum and gold is important because these by-products could potentially contribute additional Revenue and improve the overall Economics of the copper project.
PFS Becomes the Major Near-Term Catalyst
Koryx is now targeting the publication of a PFS before the end of 2026.
This is potentially the most important upcoming catalyst for TSXV:KRY because the PFS is expected to incorporate the latest drilling, resource, metallurgical and mine-planning improvements.
The company has been optimizing the Haib processing flowsheet, including the potential use of coarse particle flotation. Test work indicates that up to approximately 25% of run-of-mine material could potentially be rejected as coarse tailings while retaining limited copper losses.
If successful, this approach could potentially improve feed grade, reduce processing requirements and lower water and energy consumption.
Project Economics Could Improve
The company has indicated that flowsheet optimization could potentially improve several aspects of Haib's economics, including throughput, annual copper production, mine life and operating costs, while potentially reducing the stripping ratio and simplifying the processing route.
The updated resource itself reduced the estimated stripping ratio to 0.92x from 1.74x, an important change for a large open-pit development.
Koryx's previous development concept envisaged an average production rate of approximately 92,000 tonnes per year of clean concentrate over a 24-year mine life, although investors should await the upcoming PFS for the updated development parameters.
Drilling Programme Continues to De-Risk Haib
Koryx has been conducting an aggressive drilling campaign. Its project overview indicates that approximately 120,000 metres of drilling had already been completed, with an additional 55,000-metre program undertaken to support the PFS.
The August results follow another strong August 14 update, where 17 holes totalling more than 6,430 metres produced intervals including 831 metres at 0.27% CuEq, with 244 metres at 0.42% CuEq.
This consistency across multiple drill campaigns is potentially significant because it helps establish the geological continuity required for a large-scale open-pit development.
Namibia Infrastructure and Permitting Also Matter
Haib's development potential is also tied to infrastructure.
Koryx has outlined a potential 200 MVA power supply combining the Namibian grid with solar photovoltaic generation and battery storage. Water planning involves Supply from the Orange River together with off-site storage.
Environmental and permitting work is progressing, with 13 specialist studies completed and environmental approval targeted for H1 2027.
Zambia Provides Additional Copper Exploration Upside
Although Haib dominates the valuation story, Koryx also holds exposure to copper exploration in Zambia.
The company currently holds a 51% interest, with an option to increase to 80%, in two large Zambian Copperbelt licences covering approximately 745 square kilometres.
This provides additional exploration optionality, although the immediate investment focus remains firmly on Haib.
What Investors Should Watch Next
For TSXV:KRY, the major catalysts are further Haib assay results, completion of technical studies, the PFS targeted before year-end, metallurgical optimization, infrastructure progress and permitting.
Investors should also monitor financing requirements, Capital costs, copper-price Volatility and development execution. A large-scale copper project can require substantial capital, while the economics presented during earlier-stage studies can change as engineering and cost estimates become more detailed.
Koryx Copper Stock Outlook
The 6.67% rise in TSXV:KRY reflects growing investor attention toward Haib's combination of scale, exploration continuity and advancing development work.
The latest 969-metre mineralized intersection is particularly significant because it reinforces the sheer size and continuity of the Haib porphyry system. With the updated resource already containing more than 3.4 million tonnes of indicated and inferred contained copper combined, and a PFS targeted before the end of 2026, the company has several potentially important catalysts ahead.
The key question now is whether the upcoming PFS can translate Haib's geological scale and metallurgical improvements into compelling project economics. If it does, Koryx could attract considerably more attention as a potential long-life copper development story.
Top of Form
Bottom of Form






Please wait processing your request...