Highlights
- Construction progress at McIlvenna Bay topped the halfway mark in July 2025.
- Underground development advanced ~570 metres in July, the highest single-month progress.
- Surface ore stockpile reached ~90,000 tonnes, equivalent to over 18 days’ production.
Foran Mining Corporation reported that construction of its 100% owned McIlvenna Bay project in Saskatchewan passed the 50% completion threshold in July 2025. The company says the project remains on budget relative to the revised capital estimate disclosed on May 13, 2025, and continues to track toward commercial production targeted for mid-2026.
July represented the largest monthly surface construction advance to date, with several mechanical and structural milestones recorded. Works completed or substantially advanced during the month include ball mill lining completion, notable progress on structural steel and concrete works, installation of flotation cells, and commencement of structural steel erection for conveyor towers, tailings handling and the paste backfill structure. These surface activities underpin preparations for first production and commissioning phases.
Underground development also accelerated. Foran reported approximately 570 metres of underground development in July — the highest single-month metreage achieved to date — with daily development rates averaging nearly 20 metres per day. The company noted there were two planned downtime days to accommodate a fresh air raise vent changeover, indicating coordination between surface and underground programmes.
Operational health and safety metrics continue to be monitored as the workforce grows. The site’s lost time incident frequency rate (LTIFR) year-to-date, including exploration activities, is reported at 0.7. The project workforce numbered about 723 people on site in July, a figure that highlights the scale of mobilisation required to sustain simultaneous surface and underground workstreams.
Inventory management was a visible focus in July. Foran added roughly 28,000 tonnes to the surface ore stockpile during the month, taking the total to about 90,000 tonnes at month-end. At the project’s Phase 1 design throughput of 4,900 tonnes per day, that inventory equates to more than 18 days of steady-state production — a buffer that can aid initial mill commissioning.
The company reiterated that progress remains aligned with the revised capital estimate disclosed in May and with the mid-2026 commercial production target. Market observers will likely watch subsequent monthly updates for continuity of execution, changes in development metrics, and any adjustments to the capital or schedule baselines as the project moves from major construction into commissioning and ramp-up.