Highlights 

  • Liberty Gold secures completeness determination for the Mine Plan of Operations at Black Pine 
  • Milestone confirms the project meets federal content requirements 
  • MPO to guide the forthcoming NEPA Environmental Impact Study 
  • Stantec appointed as independent third-party EIS contractor 

Liberty Gold Corp. (TSX:LGD) has announced a key permitting milestone for its flagship Black Pine Oxide Gold Project in southern Idaho. The United States Forest Service and the Bureau of Land Management have determined that the Mine Plan of Operations meets federal content standards and is deemed “Administratively Complete.” This determination allows the project to move forward into the formal phases of federal permitting. 

The MPO outlines the proposed mining plan, processing methods, environmental safeguards, and reclamation measures for Black Pine. It is anchored in the Company’s Preliminary Feasibility Study completed in 2024 and reflects ongoing collaboration between Liberty Gold and both federal and state-level partners. 

Foundation for NEPA Review and EIS Preparation 

The completeness determination sets the stage for the National Environmental Policy Act review, one of the most significant regulatory processes for U.S. mining projects. Stantec, an international engineering and environmental consultancy headquartered in the United States, has been engaged by the USFS and BLM as the independent third-party contractor to prepare the Environmental Impact Study. 

Extensive baseline environmental studies—covering water, wildlife, vegetation, air quality, cultural resources, and socio-economic considerations—have already been completed. These will inform the EIS documents and ensure a thorough evaluation of potential project impacts. 

Liberty Gold emphasized that the MPO was developed through coordinated efforts with the Idaho Department of Environmental Quality, Idaho Department of Lands, and the Governor’s Office of Energy and Mineral Resources. An interagency Memorandum of Understanding established earlier in 2025 formalized roles and timelines, advancing smoother alignment as the project progresses through federal and state permitting tracks. 

Next Steps Toward Project Advancement 

The next formal step is the publication of a Notice of Intent in the Federal Register, which will launch the prescribed NEPA review and begin public scoping. Over the following 24 months, the process will includestakeholderengagement with Tribal Nations, local communities, federal and state agencies, and other interested parties. 

The resulting EIS will evaluate environmental and socio-economic effects, outline alternatives, and recommend mitigation measures. Liberty Gold is advancing state-level permits in parallel, including water rights, reclamation, cyanidation, and air quality authorizations, aligning with Idaho’s SPEED Act, which aims to streamline major project permitting. 

In a statement, CEO Jon Gilligan said the decision reflects years of technical and environmental work and brings the company closer to a construction decision for what it views as one of the most meaningful oxide gold development opportunities in the Great Basin. 

Conclusion 

Liberty Gold’s progress at Black Pine marks a pivotal advancement in the U.S. federal permitting process and reinforces the company’s strategy of developing open-pit oxide gold projects across the Great Basin. With the MPO now accepted and the NEPA review ready to initiate, the Company is positioned to navigate the next stages of environmental assessment and community consultation. 

Liberty Golds’ shares closed at CAD 2.16, marking a 2.37% increase from the prior session. 