Image source: © 2025 Krish Capital Pty.Ltd
Highlights
- Perseus has drilled over 35,000 meters since December 2024 at the Tusker and Kilimani deposits.
- Drilling results include intervals such as 84 meters at 3.24 g/t and 23 meters at 20.87 g/t gold.
- The work supports open pit planning and updated resource modeling at the Nyanzaga Gold Project.
Perseus Mining Limited (TSX: PRU) has released new results from its ongoing resource definition drilling program at the Nyanzaga Gold Project in Tanzania. As of June 2025, the company completed 35,623 meters of drilling across the Tusker and Kilimani deposits since its last update in December 2024.
The program is part of Perseus’s broader development plan for an open pit operation, based on the feasibility study update released in April 2025. Drilling is aimed at improving resource confidence, gathering additional geotechnical and metallurgical data, and exploring potential extensions to known mineralisation. Since acquiring the project in April 2025, Perseus has drilled a total of 58,609 meters, focusing on infill and extension work.
The company reports that the updated drill spacing across key zones has improved from 40 by 40 meters to a tighter 20 by 40 meter pattern. Recent assay results support existing geological interpretations and continue to validate mineralisation continuity at depth and along strike.
Among the more notable assay results are 84 meters at 3.24 grams per tonne (g/t) gold, 23 meters at 20.87 g/t gold, and 54 meters at 9.69 g/t gold. These intervals were intersected across several drill holes at the Tusker deposit, with additional high-grade results at Kilimani, including 44 meters at 4.36 g/t gold from surface.
Drilling remains in progress at both deposits. Results from the current phase will be incorporated into updated geological models and mine design workstreams, contributing to the ongoing assessment of Nyanzaga’s development potential.