- Validation test work confirms higher cobalt and copper recoveries from a simplified flowsheet.
- Battery-grade cobalt sulphate specifications met at SGS Canada metallurgical facilities.
- Fortune Minerals shares declined despite year-on-year gains remaining elevated.
Fortune Minerals Limited (TSX: FT) announced the completion of validation test work for an optimized hydrometallurgical flowsheet aimed at producing battery-grade cobalt sulphate heptahydrate for its NICO cobalt-gold-bismuth-copper project in Canada. The work focused on refining an existing process design to simplify operations and manage projected capital and operating cost increases, without changing the overall project scope.
The test program was conducted at SGS Canada Inc.’s Lakefield facility in Ontario and supported by funding from Natural Resources Canada, the U.S. Defense Production Act Title III program, and Alberta Innovates. According to the company, the results confirmed that high-purity cobalt sulphate heptahydrate can be produced while maintaining high metal recoveries.
Improved Recoveries and Process Adjustments
The recent tests verified cobalt recoveries of 97% and copper recoveries of 74% at the design concentrate grade. This compares with 95% cobalt and 70% copper recoveries achieved during pilot plant work completed in 2008. Tests using lower-grade, off-specification feed reported cobalt recoveries of 95% and copper recoveries of 79%, aligning with earlier pilot data.
Additional work assessed blending cobalt concentrate with bismuth leach residues before autoclave processing. This adjustment allowed recoverable gold to be captured in a single process stream, while also recovering cobalt and copper that had previously reported to the bismuth circuit. Gold recoveries in the latest tests ranged between 97% and 98%, compared with 95% in earlier studies.
Product Quality and Refinery Implications
Downstream processing steps, including solution purification, solvent extraction, evaporation, and crystallization, produced cobalt sulphate heptahydrate meeting 99.99% purity specifications required by lithium-ion battery manufacturers. Heavy metal impurity levels were reported to be within specified limits.
Bench-scale testing also indicated that a direct pre-neutralization step could remove approximately 99% of contained arsenic without oxygenation, heating, or cobalt losses. This change suggests the potential for reduced equipment sizing at the proposed Alberta refinery, which may influence future cost assumptions without altering the overall development plan.
Market Reaction and Share Performance
Despite the technical update, Fortune Minerals’ share price closed at CAD 0.10 on 20 January, down CAD 0.01, or 4.55%, on the day. Over longer periods, the stock shows mixed performance, with gains of 16.67% over the past month, 31.25% over six months, and 110.00% over the past year.