Highlights

  • Diamond drilling extended the La Verde copper-gold system to depths approaching 600 metres.
  • Multiple drillholes returned long copper-gold intercepts, with several ending in mineralisation.
  • Cash position stood at AUD 4.6 million at quarter end, with additional receipts expected.

Hot Chili Limited released its quarterly report for the period ending 31 December 2025, outlining continued expansion of the La Verde copper-gold discovery in coastal Chile. During the quarter, the company completed nine diamond drillholes totalling 3,347 metres, targeting extensions of mineralisation identified in earlier reverse circulation drilling.

Results confirmed the expansion of a bulk-tonnage, higher-grade core within the La Verde porphyry system. Drillhole DKD032 recorded 529 metres grading 0.41% copper and 0.21 g/t gold from 41 metres to end of hole, including higher-grade intervals at depth. Additional drillholes, including DKD033 and DKD034, also intersected wide copper-gold zones and ended in mineralisation, supporting continuity both laterally and vertically.

Diamond tail drilling at DKP005D extended mineralisation beyond the original hole depth, adding further copper-gold intercepts and expanding the eastern flank of the discovery. The company reported that six additional drillholes from the quarter remain pending assay results.

Near-Surface Potential and Starter Pit Considerations
The report highlighted multiple wide, near-surface copper-gold intercepts that may support the inclusion of a higher-grade starter pit within the broader Costa Fuego project. La Verde is located approximately 30 kilometres south of the planned central processing hub at Productora, allowing for potential integration into the existing mine plan.

Impact modelling referenced in the report indicates that La Verde material could add open-pit feed to the front end of Costa Fuego’s current 20-year mine schedule, potentially extending mine life and influencing project economics outlined in the March 2025 pre-feasibility study.

Project Studies and Regulatory Progress
Regulatory approval for expanded drilling at La Verde was received in October, with drill pad clearing commencing in December. The company is advancing value-engineering workstreams with Ausenco as part of ongoing project optimisation ahead of a planned feasibility study. The Environmental Impact Assessment is progressing and remains on track for submission by the end of 2026.

Cash Position and Strategic Discussions
As at 31 December 2025, Hot Chili reported cash of AUD 4.6 million and no debt. An additional AUD 2.8 million is expected from VAT refunds and joint venture recoupments, with AUD 1.8 million received in January 2026.

The company continues asset-level strategic partnering discussions for the Costa Fuego and Huasco Water projects, with multiple parties progressing through due diligence.