Cameco (TSX:CCO) shares tumbled on Friday, October 30, after the uranium giant reported a third-quarter adjusted loss and trimmed the top end of its 2026 production forecast. An extended maintenance outage at its Key Lake mill in northern Saskatchewan was the main culprit.
The stock closed at C$107.60 on the Toronto Stock Exchange, down C$9.03, after falling more than a tenth earlier in the session. It was one of the heaviest weights on the S&P/TSX Composite as the index slid about 629 points.
What happened
Cameco released its results before the market opened on Friday. Revenue was C$619 million, essentially flat with C$615 million a year earlier. Reported net Earnings rose to C$43 million from roughly break-even.
But on an adjusted basis, which strips out items such as derivative gains and losses, Cameco swung to a loss of C$2 million from adjusted earnings of C$32 million a year earlier. Analysts had expected adjusted earnings of about 23 cents a share. Adjusted EBITDA fell to C$267 million from C$310 million.
Cameco also narrowed its 2026 production guidance to 19.5 million to 20.5 million pounds of uranium, down from a range of 19.5 million to 21.5 million pounds. Sales delivery guidance was tightened to 29.5 million to 30.5 million pounds.
Why it matters
Key Lake is where ore from the McArthur River mine is milled into uranium concentrate, so downtime there ripples through the company's output and costs. Total production costs in the uranium segment rose to C$66.36 a pound from C$47.50.
Chief executive Tim Gitzel said that "we planned a longer maintenance outage at the Key Lake mill this year."
Gitzel said the mill has restarted and is producing yellowcake again, and that "we'll be back on schedule in Q4."
Lower Equity earnings from Westinghouse, the nuclear services company Cameco co-owns, also weighed on the quarter.
The bigger picture
Pricing remains a bright spot. Cameco's average realized uranium price rose to C$91.76 a pound from C$85.22 a year earlier. Gitzel said he has "never seen better fundamentals for nuclear" than in the last couple of years, but added that Cameco is "not going to front-run the market with new production" without long-term contracts in hand.
The miss landed on a brutal day for Canadian resource stocks. The materials sector fell sharply as gold dropped to a one-year low, and a tech sell-off tied to artificial-intelligence spending worries hit companies linked to data centre power demand, a theme that has helped drive interest in nuclear.
Cameco had already disappointed in the second quarter, when adjusted earnings of 18 cents a share came in at about half the consensus estimate. Friday's report added to concerns about execution at a time when investors have been paying up for exposure to the nuclear revival.
What to watch next
The company declared an annual Dividend of C$0.24 a share, payable December 15 to shareholders of record on November 30. Gitzel said Cameco has just under C$1 billion in cash.
The key test is whether Key Lake runs smoothly through the fourth quarter as promised. Any further hiccup at the mill would put the narrowed production range at risk, and investors are likely to be less forgiving a second time.
Uranium prices and new long-term Supply contracts will also be in focus, since Cameco has tied any new production to such deals. Fourth-quarter and full-year results are scheduled for February 12, 2027.