Adamera Minerals Corp. (TSX-V: ADZ; OTC: DDNFF) has announced new induced polarization (IP) survey results from its South Hedley Project near Hedley, British Columbia, expanding the Max Copper-Gold Target's chargeability anomaly to approximately 3 kilometres along strike. Survey lines L3400 and L3800 both returned strong chargeability readings, with apparent values reaching up to 59 mV/V on L3800. The anomaly remains open to the east, and preliminary readings from the in-progress line L4200 suggest continued expansion. Investors may be watching closely as the company pursues drill permits for the Max and Glix targets, both of which were submitted in February 2026.

Key Points

  • Adamera Minerals Corp. (TSX-V: ADZ; OTC: DDNFF) announced updated IP survey results from the South Hedley Project in British Columbia.
  • The Max Copper-Gold Target's chargeability anomaly now measures approximately 3–4 km wide along survey lines and approximately 3 km along strike.
  • Line L3800 returned apparent chargeability of up to 59 mV/V; the anomaly remains open to the east and at depth.
  • Drill permit applications for the Max and Glix targets were submitted in February 2026; results from approximately 2,000 soil samples collected in 2026 are pending.

Strong Chargeability Readings on Lines L3400 and L3800 at Max Target

The ongoing IP survey at the Max Copper-Gold Target uses a pole-dipole array on 5 km north-south lines spaced 400 metres apart, with seven lines completed from L1400 in the west to L3800 in the east. Line L3800 recorded apparent chargeability of up to 59 mV/V near surface, with values of 50 to 53 mV/V at the survey's deepest levels, extending over approximately 3.1 km of the line. Line L3400 reached up to 48 mV/V, with the anomaly extending over approximately 2.8 km at depth. The company notes that moderate resistivity hosting the chargeability suggests disseminated sulphides in competent host rocks.

Survey Expansion East as Line L4200 Targets Anomaly Closure

With the anomaly remaining open to the east, Adamera's IP crew is currently surveying line L4200, situated 400 metres east of L3800. Preliminary readings near the start of L4200 are described as anomalous in the release. To better define the northern extent of the IP target, L4200 will be extended an additional 500 metres north for a total survey length of 5.5 km. The company states the survey will continue east in an attempt to close off the anomaly before the end of October 2026.

South Hedley Property Context and Proximity to Copper Mountain

South Hedley covers over 24,000 hectares within the Quesnel Trough, a geological belt hosting major British Columbia porphyry copper and copper-gold mines. The Max target sits 18 km from the Copper Mountain mine, operated by Hudbay Minerals Inc. Previous soil sampling at Max returned up to 1,450 ppm copper and 1.34 g/t gold, and magnetic modelling indicates a buried intrusive body at approximately 110 metres depth. Approximately 2,000 soil samples collected at Max in 2026 are pending analysis, with results expected to provide continuous coverage over the IP anomaly.