Amex Gold Mining Inc. (TSXV: AMX) (FSE: MX00) (OTCQX: AMXEF) has announced several operational milestones at its 100%-owned Perron Gold Project near Normétal, Québec. The company reports 200 metres of underground ramp development completed, construction of a 25 kV power line underway, and the mechanical garage structure fully installed. These advances are designed to support the company's fully funded 40,000-tonne bulk sampling programme as well as planned Phase 1 mining operations.
Key Points
- Amex Gold Mining Inc. (TSXV: AMX) (FSE: MX00) (OTCQX: AMXEF)
- Underground ramp at Perron Gold Project has reached 200 metres of completed development, progressing on schedule
- A 6.5-kilometre, 25 kV power line designed to deliver approximately 3 MW is under construction, connecting the project to Normétal's existing grid
- Investors may be watching the pace of bulk sampling programme progress and infrastructure commissioning timelines
Underground Ramp Progresses on Schedule Toward Bulk Sampling Target
The company announced that its main access ramp at the Perron Gold Project has now reached 200 metres of completed underground development. The release states that work is advancing consistently and in accordance with the planned construction schedule. This ramp development forms a critical pathway toward achieving the fully funded 40,000-tonne bulk sampling programme, which remains a central near-term objective for Amex. The company did not disclose the total planned ramp length in this announcement, though the programme's advancement is described as continuous and on track.
25 kV Power Line Construction Connects Perron to Regional Electrical Grid
Construction is underway on a 6.5-kilometre, 25 kV power line linking the Perron Gold Project to Normétal's existing electrical network. The line is designed to deliver approximately 3 MW of capacity — sufficient to serve both the current bulk sampling programme and the Phase 1 mining operations outlined in the company's feasibility study published in April 2026. The release states the hydroelectric connection is expected to reduce dependence on diesel generators, lowering operating costs and supporting the project's long-term infrastructure requirements without necessitating major additional electrical investment.
Mechanical Garage and Permanent Ventilation System Installations Completed at Perron Site
Amex also announced the completion of the mechanical garage structure, which will provide dedicated facilities for the maintenance and servicing of underground mining equipment. In addition, the company states that a permanent underground ventilation system has been installed, designed to supply the required airflow volumes to ensure safe and efficient underground operations as the ramp advances toward planned bulk sample extraction zones. The release indicates that the majority of surface infrastructure required for the bulk sampling programme is now erected and approaching completion.
Infrastructure Build-Out Supports Phase 1 Mining Ambitions at Perron
President and CEO Victor Cantore stated in the release that the company is building infrastructure intended not only to support the current bulk sampling programme but also to underpin future Phase 1 mining operations. The Perron Gold Project encompasses 183 contiguous claims covering 65.72 km² and hosts several high-grade gold mineralisation zones. The release notes the project benefits from year-round road access, proximity to Normétal, and closeness to processing facilities operated by major gold producers. The immediate share price impact was not clear from available public information.