Ares Strategic Mining Inc. (CSE: ARS) has announced the official commencement of commissioning at its Metallurgical Lumps Plant in Delta, Utah, marking the first time the entire processing facility has operated as a fully integrated system. The company expects to begin ramp-up production on August 15, 2026, following a four-week comprehensive testing program designed to verify performance and optimize operations before commercial production commences.

Key Points

  • Ares Strategic Mining Inc. (CSE: ARS) has begun commissioning of its Metallurgical Lumps Plant at its processing facility in Delta, Utah.
  • The plant is designed to process ore from the Lost Sheep Mine into metallurgical-grade fluorspar (metspar) for supply to U.S. steel industries.
  • The company expects ramp-up production to begin on August 15, 2026, following a four-week commissioning program involving comprehensive integrated testing across all plant systems.
  • The Lumps Plant has a designed processing capacity of approximately 150,000 tonnes per annum, with commercial offtake agreements already in place covering the first five years of expected initial metspar production.

Full Operational Integration Marks Critical Facility Milestone

Ares Strategic Mining announced on July 21, 2026, that its Metallurgical Lumps Plant at the Delta, Utah processing facility has officially commenced commissioning operations. The disclosure represents a significant operational milestone for the company, as the entire processing plant has been powered up and is now operating as one fully integrated system for the first time since construction completion.

The announcement emphasizes that this represents the beginning of the company's four-week commissioning program. During this period, Ares will undertake comprehensive testing to verify that all systems function correctly and are optimized for commercial production. This integrated approach to plant startup is designed to ensure that ore processing from the Lost Sheep Mine can flow seamlessly through the facility to produce finished metallurgical-grade fluorspar lumps intended for the U.S. steel industry.

Comprehensive Testing Program Across Plant Systems

The commissioning process involves multiple testing activities across all operational areas of the Lumps Plant. The company will verify complete process flows from ore feed through to finished product, ensuring that material moves through the facility as designed. Additionally, testing will focus on programmable logic controller (PLC) control systems and human-machine interface (HMI) systems that manage plant operations, a critical component for reliable, automated operation once production begins.

Beyond systems verification, the company will monitor and optimize operating parameters including temperatures, pressures, and material flows throughout the facility. Ares will also validate alarm systems, diagnostics, and automated start-up and shutdown sequences to ensure safe and reliable operation. Quality assurance testing will assess crushing, drying, and product specifications to confirm that metallurgical-grade fluorspar meets customer requirements before commercial shipments commence.

August 15, 2026 Production Ramp-Up Target

The company disclosed that it expects ramp-up production to begin on August 15, 2026. Ramp-up production refers to the gradual increase of feed material to the plant as it works toward full production potential. This phased approach allows the company to validate operations under load conditions while maintaining quality standards and ensuring all systems perform reliably.

To support testing and initial ramp-up production runs, fluorspar ore stockpiled at the Lost Sheep Mine in Utah will be transported to the Delta processing facility. This ore supply will enable Ares to conduct realistic production testing before commencing full commercial operations. The staged approach to ramping production provides an additional buffer to identify and address any operational issues before the facility reaches its designed capacity.

Pre-Existing Commercial Offtake Agreements Secure Market Access

Ares has previously disclosed that commercial offtake agreements are already in place to cover the company's expected initial metspar production for the first five years of operation. This commitment from offtake partners de-risks the commercial launch by providing confirmed buyers for the facility's initial output, allowing the company to proceed with confidence toward production commencement.

The existence of pre-arranged offtake agreements suggests that market demand for metallurgical-grade fluorspar remains solid in North America, particularly among steel producers who represent the primary end-use market for this mineral. The agreements cover an extended five-year window, providing revenue visibility during the critical ramp-up and early production phases.

Designed Production Capacity Supports Future Growth

The Lumps Plant has been designed with a processing capacity of approximately 150,000 tonnes per annum. The company has disclosed that this capacity extends well beyond its initial mining rate, positioning the facility to support increased output from the Lost Sheep Project and potential expansion across the wider Spor Mountain Range. This capacity architecture provides a platform for future growth as Ares develops additional fluorspar targets across its property portfolio.

Management commentary indicates that the company has intentionally built infrastructure that can scale with future mining expansion. This forward-looking approach allows Ares to pursue strategic growth opportunities without requiring significant additional capital expenditure on processing capacity. The substantial designed capacity suggests that the company views its Utah fluorspar operations as a cornerstone asset with multi-decade production potential.

Lost Sheep Project Assets and Regulatory Approvals

The Lost Sheep Fluorspar Project comprises 5,982 acres encompassing 353 mining claims in the Spor Mountain area of Juab County, Utah, located approximately 214 kilometres south-west of Salt Lake City. Ares holds 100 per cent ownership of this project, which has been fully permitted, including mining permits necessary for ore extraction operations.

The project's mining plan has been approved by the U.S. Bureau of Land Management (BLM). The initial approval was granted on August 24, 1992, and was subsequently renewed on December 12, 2016. A National Instrument 43-101 technical report has identified high-grade fluorspar reserves with low levels of impurities, providing the geological foundation for the company's production plans. These regulatory approvals and technical documentation establish the project as a permitted, authorized mining operation in good standing with U.S. federal authorities.

Metallurgical Fluorspar Market and End-Use Applications

Metallurgical-grade fluorspar (metspar) serves as a critical input for the U.S. steel industry, where it is used as a flux in steel-making processes. Fluorspar is also utilized in the production of chemicals and specialized industrial materials vital to modern technology and infrastructure. The company's strategic positioning to supply high-grade fluorspar to North American markets aligns with broader efforts to strengthen domestic supply of this mineral commodity.

The mineral's importance to domestic manufacturing has made fluorspar a focus commodity for U.S. supply security initiatives. Ares's objective of becoming a significant supplier of high-grade fluorspar to North American markets directly addresses supply chain priorities within the North American steel and manufacturing sectors. The pre-existing offtake agreements suggest that potential buyers are actively seeking additional domestic sources to reduce import dependence.

Forward-Looking Operational Transition and Risk Considerations

The company has provided explicit forward-looking statement language in its announcement, noting that while comprehensive feasibility studies are typically completed before production decisions, industrial mineral ventures such as Ares's fluorspar operation are sometimes relatively simple operations with lower investment and technical risk. The company states that it has based its production decision on historical engineering work, geological reports, historical production data, and current engineering work.

Investors should note that the company has disclosed material risks associated with the production decision, including the acknowledgment that ventures proceeding to production without formal prefeasibility or feasibility studies conforming to NI 43-101 standards have historically carried higher risk of economic or technical failure. However, the announcement indicates that management has determined such formal studies are not required for this particular production decision based on the nature of the operation and available historical data.

CEO Commentary on Project Progression

James Walker, President and Chief Executive Officer of Ares Strategic Mining, commented that seeing the entire Lumps Plant operating together for the first time represents an exciting milestone reflecting years of planning, engineering, and construction. Walker stated that the company's focus is now on completing commissioning successfully and beginning production.

Walker also noted that the company has intentionally built processing infrastructure extending well beyond its initial mining rate, positioning the facility as a platform for future growth while supporting the company's objective of establishing a secure U.S. supply of this critical mineral. These comments underscore management's longer-term vision for the operation beyond the immediate production commencement.