Excellon Resources Inc. (TSXV: EXN) (OTC Pink: EXNRF) (FSE: E4X2) announced it has achieved first concentrate production during the pre-commissioning campaign at its 100%-owned Mallay Silver-Lead-Zinc Mine in central Peru. Since restarting on July 2, 2026, the concentrator has processed approximately 12,000 tonnes of material, producing concentrates containing roughly 29,200 ounces of silver, 319,000 pounds of lead, and 456,000 pounds of zinc. Initial concentrate shipments are expected in August 2026, marking a significant operational milestone for the company's restart program.

Key Points

  • Excellon Resources Inc. (TSXV: EXN) (OTC Pink: EXNRF) (FSE: E4X2)
  • First concentrate production achieved at the Mallay Mine during the pre-commissioning campaign that began July 2, 2026
  • Concentrator has processed approximately 12,000 tonnes; mill throughput targeted at approximately 400 tonnes per day; initial shipments expected August 2026
  • Investors may be watching the 400 Ramp rehabilitation timeline and upcoming drill results from three active rigs

Mallay Concentrator Output and Mill Pre-Commissioning Performance

The Mallay concentrator, a conventional flotation plant with a nameplate capacity of 600 tonnes per day, has operated without unplanned shutdowns since its July 2, 2026 restart. The pre-commissioning campaign has yielded two concentrate products — a lead-silver concentrate and a zinc concentrate. The company is deliberately holding mill throughput at approximately 400 tonnes per day to allow its metallurgical team to optimise reagent addition, grinding, and flotation performance during ramp-up. The company noted that metal quantities referenced are contained in concentrate and are not payable metal, and that production figures are derived from internal, unaudited operating data subject to verification.

400 Ramp Dewatering Clears Path to Deeper Mineralisation

A parallel operational advance centres on the 400 Ramp, the principal underground accessway to mineralisation below the 4090 Level. The release states that dewatering has drawn the water level down by approximately 45 metres from the 4090 Level, enabling rehabilitation to begin. Rehabilitation is expected to take approximately three months. Once complete, the company anticipates transitioning from labour-intensive cut-and-fill mining methods — historically used on narrower vein widths above the 4090 Level — toward bench-and-fill methods that may support greater mechanisation and improved long-term productivity, according to the announcement.

Drilling Campaign Targets Depth Confirmation and Near-Mine Growth

Three drill rigs are currently active at Mallay, targeting confirmation drilling at depth and near-mine exploration. Chief Operating Officer Paul Keller noted in the release that drilling is defining wider mineralised zones below the 4090 Level compared to the narrower veins historically mined, which the company believes could support a more productive operation over time. Results from the ongoing drill program are expected to be reported separately. The company also stated that updated mine planning and scheduling is underway, with a restart plan and schedule update targeted for the third quarter of 2026.