Gold Port Corporation (CSE: GPO | OTCQB: GPOTF) announced on September 10, 2026 that construction of the access road to its Groete Gold Copper Project in Guyana is nearing completion. Debrushing has reached within 1 mile of the Gold Port Camp, four bridges have been completed or replaced, and the crew is preparing to build the final bridge over a large creek. The milestone is significant for investors as completion of the access road is described as a direct precursor to the company's planned drill program at Groete.
Key Points
- Gold Port Corporation (CSE: GPO | OTCQB: GPOTF)
- Access road construction at the Groete Gold Copper Project in Guyana is nearing completion, with the final bridge over a large creek to be built next
- Road width has been increased by sixty percent over the prior trail system; a laterite source has been located and road material stockpiled; the company's MP Explorer track-mounted diamond drill will be recommissioned upon access completion
- Investors may be watching for confirmation of access road completion and the formal launch of the drill program at the 100%-owned Groete project
Road Construction Progress at the Groete Gold Copper Project
The access road runs from the Manaka Road on the east bank of the Essequibo River to the drill site at Groete Creek. The release states that debrushing is now complete to within 1 mile of the Gold Port Camp, the road has been widened by sixty percent compared to the prior trail system, and a source of laterite has been identified with road material stockpiled for future use. Two all-season bridges have been completed and two existing culverts have been replaced with bridges, leaving one final bridge over a large creek still to be constructed.
Diamond Drill Recommissioning Tied to Access Completion
In anticipation of access road completion, the company announced that its MP Explorer track-mounted diamond drill, currently held in storage, will be recommissioned for service. The release frames the infrastructure build as the foundational first step toward supporting the upcoming drill program at Groete. The company states that management is planning to keep the project progressing efficiently and on schedule while maintaining construction standards. The company did not disclose a specific timeline or cost for the recommissioning process in the announcement.
Groete Project Mineral Resource and Exploration Background
Gold Port holds a 100% interest in the Groete Gold Copper Project in Guyana, where exploration began in 2012. A January 2019 Inferred Mineral Resource calculation estimated 1.57 million gold-copper equivalent ounces, comprising approximately 1.1 million gold ounces and 195 million pounds of copper within 74 million tonnes. The resource carries an Au grade of 0.49 grams per tonne and a Cu grade of 0.12%. These figures were calculated using a gold price of US$1,275 per ounce and a copper price of US$3.00 per pound, at a cut-off grade of 0.25 gold equivalent grams per tonne.