i-80 Gold Corp. (NYSE: IAUX / TSX: IAU) has announced the commencement of production mining at its Archimedes underground project on the Ruby Hill property in Nevada, marking the company's second underground mine to come online. The milestone was achieved on schedule, with both oxide and sulphide material now being extracted from the high-grade deposit in the Battle Mountain-Eureka gold trend. The development advances i-80 Gold's hub-and-spoke processing strategy and brings the company a step closer to its consolidated annual gold production target of 150,000 to 200,000 ounces beginning in 2028.

Key Points

  • i-80 Gold Corp. (NYSE: IAUX / TSX: IAU) announced first production mining at its Archimedes underground project in Nevada
  • Production commenced on schedule, with oxide material placed on the Ruby Hill heap leach pad and sulphide material stockpiled for the Lone Tree Plant
  • Total project capital is expected to be approximately $10 million higher than the $47.3 million estimated in the March 2025 PEA, due to expanded surface infrastructure
  • Investors may be watching for 2027 production guidance expected early in the new year and the planned Archimedes feasibility study in the second half of 2027

Archimedes Underground Reaches Production Milestone on Schedule

i-80 Gold confirmed that production mining commenced following completion of required surface and underground infrastructure, including ventilation and escape raises. Lateral development at the project totals approximately 3,600 metres to date, and ground conditions remain favourable. The release states that the underground contractor has exceeded planned productivity rates within the upper 426 Zone. Construction of additional infrastructure — including further ventilation raises, a permanent mine dry, and offices — is set to continue through 2027 to support the planned ramp-up in mining rates.

Oxide Material Directed to Heap Leach Pad, Gold Recovery Expected in Early 2027

Beginning in mid-November, oxide material mined from the upper 426 Zone was placed on the existing heap leach pad at Ruby Hill, with gold recovery expected to begin in the first quarter of 2027. The company indicates that metallurgical test work has confirmed the oxide material is amenable to heap leaching at lower overall processing costs compared to its oxide mill circuit at Lone Tree Plant. With the majority of mineralized material mined in 2027 expected to be oxide, i-80 Gold states it anticipates being able to increase its heap leach production outlook, though full guidance will be provided early in the new year.

Archimedes Resource Base and 2027 Feasibility Study Drilling Under Way

As of December 31, 2025, Archimedes hosts an Indicated Mineral Resource of 1.8 million tonnes grading 7.6 grams per tonne gold for 436,000 ounces, and an Inferred Mineral Resource of 4.2 million tonnes grading 7.3 grams per tonne for 988,000 ounces. Seven underground drill rigs are currently active, targeting approximately 55,000 metres across 140 drill holes. The drilling campaign is expected to be completed in the second quarter of 2027 and is designed to support an Archimedes feasibility study planned for the second half of 2027.