Lithium X2 Mining Inc. (TSXV: LIXX) has released an independent NI 43-101 technical report supporting its 2026 Pre-Feasibility Study (PFS) for the Nevada North Lithium Project (NNLP) in Elko County, Nevada. The report, prepared by lead consultant Fluor Enterprises, Inc., confirms an after-tax NPV of US$9.81 billion at an 8% discount rate and an IRR of 23.6%, based on a lithium carbonate price assumption of US$24,000 per tonne. The disclosure marks the first Mineral Reserve estimate for the project and establishes the full engineering and economic basis for a proposed 42-year operation. Investors may be watching the results closely given the scale of the projected economics.
Key Points
- Lithium X2 Mining Inc. (TSXV: LIXX | OTCQX: LIXMF | FSE: 9WI)
- Independent NI 43-101 technical report filed, supporting PFS results first announced October 2, 2026, with no material differences reported
- Proven and Probable Mineral Reserve of 218.3 Mt at 3,928 ppm Li containing 4.56 Mt LCE; total project CAPEX of US$5.12 billion across two phases; after-tax payback of 4.2 years
- Investors may be watching progress on the feasibility study, pilot plant testing, and permitting milestones disclosed by management
NNLP Pre-Feasibility Economics and Reserve Estimate
The PFS outlines average annual production of approximately 92,250 tonnes of battery-grade lithium carbonate over a 42-year mine life, with overall lithium recovery of 84.9%, up from 82.8% in the 2025 Preliminary Economic Assessment. Operating costs are reported at US$4,719 per tonne of lithium carbonate, 10% lower than the prior PEA. The life-of-mine after-tax undiscounted cash flow is stated at US$56.3 billion. The after-tax NPV8% is reported as remaining positive across a ±30% range in every sensitivity variable tested, according to the technical report.
Two-Phase Construction Plan and Capital Cost Breakdown
The lithium plant is designed to be built in two phases, each comprising a processing train with a design capacity of approximately 55,900 tonnes per year of battery-grade lithium carbonate. Phase 1 capital cost is stated at US$2.77 billion and Phase 2 at US$2.35 billion, for a combined total of US$5.12 billion. Sustaining capital is disclosed at US$1.65 billion. The company notes all material is expected to be free digging, and the waste-to-ore ratio is 0.88:1. Phase 1 capital and operating cost estimates are classified as AACE Class 4, carrying a ±25% accuracy range.
Joint Venture Structure and Project Location
The NNLP is held through Nevada North Lithium LLC, a joint venture owned 67.5% by Lithium X2 and 32.5% by Evolution Mining Limited. The project is located approximately 74 kilometres north of Wells, Nevada, accessible via U.S. Highway 93. The technical report presents an updated Mineral Resource estimate with an effective date of July 20, 2026, which adds cesium and rubidium as accessory metals, though neither is included in the Mineral Reserve or the economic analysis. Lithium tonnes, grades, and contained LCE are reported as unchanged from the October 2, 2026 estimate.