MetalQuest Mining Inc. (TSX.V: MQM) has received an independent NI 43-101 technical report on its 100%-controlled Superior Iron Project in northern Québec, prepared by John Langton, M.Sc., P.Geo., of JPL GeoServices Inc., with an effective date of August 14, 2026. The report recommends a staged, two-phase exploration program totalling $990,000, targeting both iron formation in the project's northern section and potential massive-sulphide and graphite mineralisation in the east. The disclosure marks the first formal independent assessment of the greenfield project, which covers 24,579 hectares and has no defined mineral resources.

Key Points

  • MetalQuest Mining Inc. (TSX.V: MQM) received an independent NI 43-101 technical report on the Superior Iron Project
  • Qualified Person John Langton recommends a two-phase exploration program totalling $990,000 CAD
  • Phase 1 is budgeted at $275,000 for target generation; Phase 2 at $715,000 for trenching and diamond-drilling, contingent on Phase 1 results
  • Investors may be watching for results from a recently completed airborne geophysical and LiDAR survey, which the company states will be reported separately

Superior Iron Project Location, Scale, and Two Target Types

The Superior Iron Project comprises 510 exclusive exploration rights covering 24,579 hectares in Québec's Kativik Territory, approximately 160 km northwest of Schefferville. The project is accessible only by air. The technical report identifies two distinct target types: Sokoman Formation iron formation grading 20–40% iron in the northern portion, and Menihek Sub-Group rocks in the eastern arm considered prospective for exhalative massive-sulphide and graphite mineralisation. The project surrounds MQM's adjacent Lac Otelnuk iron project, though the company cautions that mineralisation at Lac Otelnuk is not necessarily indicative of mineralisation on the Superior Iron Project.

August 2026 Site Visit Confirms Geology Consistent with Underlying Stratigraphy

On August 5, 2026, Qualified Person John Langton visited the project, conducted an aerial examination by float plane, and reviewed historical drill core stored at Camp Alpha. His key finding, as stated in the technical report, was that rock types in the core match those interpreted to underlie the project, specifically the Ashuanipi, Seward, Pisolet, Wishart, Ferriman, and Menihek stratigraphic units — the same package hosting iron formation at Lac Otelnuk. Langton confirmed all 510 exclusive exploration rights were in good standing as of the August 14, 2026 effective date and is independent of MQM with fees not contingent on results.

Staged $990,000 Budget Prioritises Data Building Before Drilling Commitment

The technical report describes the Superior Iron Project as essentially virgin territory with little geological or geochemical data. Mr. Langton's recommended Phase 1 program of $275,000 covers geological mapping, prospecting, litho-mineralogical study, soil geochemical sampling, and localised geophysical surveys. Phase 2, budgeted at $715,000, advances to trenching, stripping, bulk sampling, and diamond-drilling, but only proceeds if Phase 1 identifies anomalous geochemistry or mineralisation. The company notes that a recently completed airborne geophysical and LiDAR survey is currently being evaluated and results will be disclosed separately.