Pasinex Resources Limited (CSE: PSE) (FSE: PNX) has resumed exploration drilling at its Pinargozu Zinc Mine in Türkiye for the first time in approximately two years, the company announced on November 10, 2026. The restart follows the dissolution of the previous joint venture that had managed the mine, and marks a significant operational milestone for the Toronto-based, zinc-focused miner. An approximately 4,000-metre underground drilling program is now underway, targeting deeper sulphide mineralisation that has not yet been mined. Investors may be watching the program closely for results that could inform the company's longer-term production plans at Pinargozu.
Key Points
- Pasinex Resources Limited (CSE: PSE) (FSE: PNX) is a Toronto-based zinc-focused exploration and development mining company
- Exploration drilling restarted at Pinargozu on October 7, 2026, with the first of three planned drill stations now reached and active
- As of November 5, 2026, 207.5 metres of underground drilling had been completed; the full program totals approximately 4,000 metres across three stations
- Investors may watch for drill results from the deeper +410 level and updates on the Teksomak short-hole drilling program supporting production
Pinargozu +410 Development Advances to First Drill Station
Drilling at Station 1 commenced on October 7, 2026, using a Diamec U6 underground drill rig. As of November 5, 2026, two drill holes had been completed — PPU26-001 at 110 metres and PPU26-002 at 97.5 metres — with a third planned to further test down-dip continuity of mineralisation. The +410 main drift has advanced 125 metres of its planned 700-metre total, with 60 metres of drill-station drifts and 22.5 metres of the planned raise also completed. The remaining approximately 575 metres of the main drift is expected to be finished in the third quarter of 2027, subject to ground conditions and equipment availability.
Three-Station Program Targets Deeper Sulphide Mineralisation
The approximately 4,000-metre drilling program is designed to test the deeper, down-dip continuation of sulphide mineralisation previously mined above the +541 Gallery, as well as to follow up on zinc mineralisation intersected in 2023. Drill hole PPU23_072, completed during that earlier program, intersected 1.50 metres grading 44.03% zinc (XRF) from 120.80 metres downhole — though the company notes XRF results are indicative and are not a substitute for laboratory assay results, and that true widths have not been determined. Stations 2 and 3 are each planned for approximately 1,500 metres and will be accessed as development of the +410 drift continues.
Second Rig Deployed for Short-Hole Drilling Around Previously Mined Zones
Alongside the deeper +410 program, Pasinex has set up a Teksomak Explorer drill rig at the +570 level of the +541 Adit to conduct short-hole drilling targeting narrow vein extensions surrounding previously mined zones. The release states this program aims to support production operations and assist in evaluating mineralisation geometry. The two-rig approach reflects the company's effort to simultaneously advance exploration and sustain operational continuity at Pinargozu.
Annual General Meeting Scheduled for December 2026
The company's annual general meeting of shareholders is scheduled for December 17, 2026, at 11:00 a.m. Eastern Time in Toronto, Ontario. The record date for shareholder voting eligibility is November 12, 2026. Shareholders will be asked to elect directors, appoint auditors, approve a restricted share unit plan, and consider other customary business. The immediate share price impact of the exploration update was not clear from available public information.