Quebec Innovative Materials Corp. (CSE: QIMC) has announced a structured five-phase program to test hydrogen extraction at its Bennett Hill property in Nova Scotia, managed by Halifax-based independent firm Strum Consulting. The company states it is fully funded for Phases 1 through 4 from existing cash resources, requiring no additional financing. With preliminary drill results showing hydrogen concentrations of up to 30.0% in one hole and near-zero methane readings, investors may be watching closely as the project advances toward a potential commercial extraction pilot.
Key Points
- Quebec Innovative Materials Corp. (CSE: QIMC, OTCQB: QIMCF, FSE: 7FJ) announced the five-phase program on November 17, 2026.
- Strum Consulting of Halifax will manage in-situ hydrogen characterisation and hydrogeological testing across drill holes DDH-26-04 and DDH-26-05 at Bennett Hill.
- Preliminary mud-gas samples returned hydrogen of up to 24.3% in DDH-26-04 and up to 30.0% in DDH-26-05, with methane at approximately 0% in both holes.
- Investors should watch for phase-by-phase results disclosures and the company's planned submission to IESO Nova Scotia, which closes January 30, 2027.
Bennett Hill Drilling Results and Current Project Status
QIMC has completed two drill holes at Bennett Hill, approximately 700 metres apart. DDH-26-04 reached 818 metres and was completed in July 2026, while DDH-26-05 is currently at approximately 416 metres. Pressurised gas and water reached surface during drilling in both holes. The company's 2026 seismic survey identified a deep fault beneath both holes, which QIMC interprets as the primary pathway for hydrogen rising from depth. The company notes these preliminary results are from mud-gas headspace samples and do not establish in-situ dissolved concentrations, sustained flow rates, or recoverable volumes.
What the Five-Phase Strum Consulting Program Will Measure
The program begins with extending DDH-26-05 beyond 1,000 metres to reach the deep fault, with Maritime Drilling resuming work in November 2026. Subsequent phases involve taking pressurised gas and water samples, isolating individual zones using inflatable packer plugs to test pressure and flow, and conducting an extraction test drawing free gas from shallow zones while pumping hydrogen-bearing water from depth. Phase 5 focuses on designing a pilot extraction program. International engineering firm Tetra Tech has been engaged to assist with pre-engineering work required for the IESO Nova Scotia submission.
No-Fracking Extraction Model and Funding Position
QIMC states the Bennett Hill extraction concept relies on natural fractures to deliver hydrogen without hydraulic fracturing or reservoir stimulation. Shallow wells would capture free gas while deep wells, all under 1,000 metres, would pump hydrogen-bearing water to surface for separation, with water returned underground to maintain pressure. Membrane separation technologies will also be tested downhole. The company confirmed it is fully funded for Phases 1 through 4 from existing cash, with no additional financing required. The company will report results as each phase is completed.