Quebec Innovative Materials Corp. (CSE: QIMC | OTCQB: QIMCF | FSE: 7FJ) has announced a detailed five-phase program to test hydrogen extraction at its Bennett Hill project in Nova Scotia, with independent firm Strum Consulting of Halifax leading hydrogeological measurements. The fully funded program requires no hydraulic fracturing and is designed to proceed under existing permits and authorisations. Investors may be watching the initiative closely as it represents the company's clearest path yet from exploration toward a commercial hydrogen extraction pilot.

Key Points

  • Quebec Innovative Materials Corp. (CSE: QIMC) is a Montreal-based natural hydrogen exploration company active in Nova Scotia, Québec, Ontario, and Minnesota
  • QIMC has outlined a five-phase characterisation and extraction-testing program at its Bennett Hill drill holes DDH-26-04 and DDH-26-05
  • Mud-gas headspace samples returned hydrogen concentrations of up to 24.3% in DDH-26-04 and up to 30.0% in DDH-26-05; no resource or reserve has been defined
  • Investors should watch phase-by-phase results as the company states it will report outcomes as each phase is completed

Bennett Hill Drilling Results Supporting the Five-Phase Design

The company has drilled two holes at Bennett Hill, located approximately 700 metres apart. DDH-26-04 reached 818 metres and was completed in July 2026, while DDH-26-05 is currently at approximately 416 metres. Mud-gas headspace samples returned hydrogen concentrations of up to 24.3% in DDH-26-04 and up to 30.0% in DDH-26-05, with methane reported at approximately 0% and CO₂ at or below 0.2% in both holes. The company's 2026 seismic survey identified a deep fault beneath both holes, which QIMC interprets as the main hydrogen migration pathway. These results were previously disclosed in earlier company releases.

What Strum Consulting's Five Phases Will Measure at Bennett Hill

Halifax-based Strum Consulting will serve as independent third-party program manager and hydrogeological lead. The five phases cover: extending DDH-26-05 to beyond 1,000 metres to reach the deep fault, with drilling resuming in November 2026; measuring dissolved hydrogen concentrations in pressurised water samples from both holes; isolating individual zones with inflatable packers to test pressure, flow, and recharge rates; running an extraction test drawing free gas from shallow zones and pumping hydrogen-bearing water from depth; and designing a pilot extraction program based on the gathered data. No fracking or reservoir stimulation is involved at any stage.

Funding Position and IESO Nova Scotia Submission

The company states it is fully funded to complete Phases 1 through 4 from existing cash resources, with no additional financing required. For Phase 5, QIMC has engaged international engineering firm Tetra Tech for pre-engineering work in connection with a planned submission under IESO Nova Scotia's technology-neutral Request for Qualifications for new energy storage and on-demand electricity generation, which the announcement states closes January 30, 2027. The company notes that filing a submission does not guarantee qualification or a contract award.