Sixty North Gold Mining Ltd. (CSE: SXTY) announced on July 16, 2026, that development activities at its wholly-owned Mon Gold Mine in Yellowknife, NWT are proceeding on schedule with only modest delays. The company has assembled its camp, received authorization to clear the mill pad, and commenced road construction to the dry stack tailings facility, with a revised Design and Construction Plan submitted to the Mackenzie Valley Land and Water Board for review. The announcement reflects progress toward the company's goal of commencing gold production this year, contingent on regulatory approvals.
Key Points
- Sixty North Gold Mining Ltd. (CSE: SXTY) is developing the Mon Gold Mine, a 100-per-cent-owned underground gold operation in Yellowknife, NWT
- The company has received authorization from inspectors to clear the mill pad and commence road construction to the dry stack tailings facility
- A revised Design and Construction Plan for the mill has been submitted to the Mackenzie Valley Land and Water Board; crews are on-site executing initial mobilization and infrastructure construction activities
- The timeline for commencing operations depends on approvals of remaining Management Plans, including the Water and Groundwater Management Plan, which is subject to a board directive for two years of post-2023 wildfire baseline sampling
Camp Assembly and Site Infrastructure on Track
Sixty North Gold reported that crews have assembled the company's camp and are actively executing site operations. The company indicated that camp and infrastructure assembly is expected to require 3 to 4 weeks, with crews already on-site and active according to the announcement. This mobilization represents a foundational step in preparing the Mon Gold Mine for transition from the Advanced Exploration Plan phase toward full production operations.
Parallel to camp assembly, the company has received authorization from inspectors to commence clearing blasted rock from the mill pad and to begin constructing roads to the dry stack tailings facility. The clearing and road construction phase is anticipated to span approximately 2 weeks, with crews scheduled to commence within the next 2 weeks of the announcement date. These activities reflect progression of the physical infrastructure necessary to support milling operations once equipment assembly and regulatory approvals are finalized.
Mill Assembly and Construction Plan Under Review
The company disclosed that mill assembly is expected to commence once approvals of the revised Design and Construction Plan are received from the Mackenzie Valley Land and Water Board. The mill assembly phase is projected to require 9 to 13 weeks, contingent on regulatory clearance. Sixty North Gold has submitted a revised Design and Construction Plan for the mill facility to the MVLWB, reflecting engagement with the regulatory review process.
The 100 tonnes per day mill is designed as a crush, grind, gravity, float, filter dry stack operation, representing what the company describes as the first environmentally friendly mill design in the Yellowknife gold belt. Extraction of mill feed is scheduled to commence one week prior to mill start-up, though no specific timeline was disclosed for when full operational production would begin. All remaining approvals are prerequisites before the mill can transition from assembly to processing.
Regulatory Engagement on Water Management and Environmental Assessment
Discussions with the Mackenzie Valley Land and Water Board regarding the water management plan are ongoing. The company stated it has submitted an independent review of 25 years of sample results to support its position on water conditions, with particular focus on demonstrating that no significant change in water conditions occurred after material wildfire seasons in 2023 and other years. The company attributed missing data at sample sites to drought conditions that reduced or eliminated water availability in advance of wildfire seasons.
In June 2026, Sixty North Gold initiated and completed a more extensive Archeological Impact Assessment following an earlier Archeological Overview Assessment that included field visits in 2016. The company stated this expanded assessment was undertaken to provide greater confidence to local First Nations that the Mon Gold Mine will have minimal and acceptable environmental and cultural impacts. All Management Plans have been submitted at least once to regulators, with the Water and Groundwater Management Plan remaining subject to a board directive requiring two years of post-2023 wildfire baseline sampling data.
Operational Approach and Gold Recovery Technology
The Mon Gold Mine employs selective underground mining from a single 3-meter by 4-meter access portal with one 2-meter by 2-meter raise for secondary egress, designed to produce minimal waste rock. Mill feed is developed and trucked to surface as needed. The processing circuit begins with crushing in a closed two-stage circuit before material enters a ball mill for grinding to p80 minus 150 mesh. The company selected a coarser grind specification because test work demonstrated recovery of greater than 95 percent of gold, resulting in coarser tailings that are easier to manage than finely ground rock.
Gold recovery employs a gravity circuit where concentrate can be melted to form raw gold or doré bars. Gravity tailings pass to a flotation circuit for processing of residual gold. The company did not disclose the specific cumulative recovery rate between the two circuits in this announcement. Gold flotation concentrate and associated sulphides are collected into mega bags for shipment off-site for sale or further processing. Tailings are filtered in pressure filters to remove 80 to 85 percent of water for recycling, with residual damp sands trucked to the dry stack facility for placement and monitoring.
Water Management and Environmental Sustainability Design
The 100 tonne per day mill requires 15 to 20 cubic meters of make-up water daily, sourced first from mine water discharge and, if necessary, from fresh water sources. According to the company, the Mon Mine should use less water than a modest diamond drill program and have no liquid slurry to manage. The filtration and recycling approach is designed to reduce fresh water usage by greater than 85 percent compared to conventional milling operations.
The dry stack tailings facility approach eliminates the need for traditional tailings ponds or liquid slurry management. Damp sand tailings comprised of quartz, carbonate, and minor rock fragments are placed in the dry stack facility where they can be monitored over time. This design reflects the company's stated commitment to sustainable operations in the Yellowknife region.
Underground Development and Ore Zone Expansion
Historical mining at the Mon Gold Mine during the 1990s extracted 15,000 tonnes of ore to depths of only 15 metres below surface, recovering an estimated 15,000 ounces of gold according to the company's technical report filed with SEDAR+ on August 3, 2023. Recent underground development has intersected the productive A-Zone at 17 metres below the historic stopes as planned, indicating the ore body extends significantly deeper than previous exploitation. The company identified a newly discovered zone, the DD-Zone, which is exposed in the main ramp.
Development plans include mining stopes in the East Limb, West Limb, and DD Zone, with extension of the ramp to allow development of deeper levels. The company also identified silver-rich volcanogenic massive sulphide (VMS) deposits, large shear zone-hosted gold targets, and critical-element-enriched iron oxide copper gold (IOCG)-style mineralization on its property for exploration and development as warranted. These additional mineral systems provide potential future expansion opportunities beyond the initial Mon Gold Mine development.
Historical Context and Yellowknife Gold Camp Positioning
The Yellowknife gold camp has historically hosted significant gold production. The company noted that two mines in the camp, including Discovery Mine and the Mon Mine itself, averaged 30 grams per tonne of gold or better. An additional two mines, Con Mine and Giant Mine, averaged 15 grams per tonne or better, with the four operations collectively producing over 14 million ounces of gold historically. All of these historic mines commenced production at less than 100 tonnes per day according to the company's technical report.
Sixty North Gold positions Yellowknife as possessing the necessary people, services, and mining experience to revive the Archean gold belt's production history. The company's 100 tonne per day operation scale aligns with the historic pattern of initial production rates in this region, suggesting the operational model is consistent with the camp's proven development pathway.
Funding Status and Expert Support for Project Completion
The company stated it is well funded and has engaged external technical experts to assist in completion of remaining Management Plans required for regulatory approval. No specific funding amount, debt level, or capitalization details were disclosed in the announcement. The engagement of external expertise reflects the company's approach to meeting regulatory requirements and ensuring technical quality of submitted documentation.
Dr. D.R. Webb, P.Geol, P.Eng., who serves as President and CEO of Sixty North Gold and is a qualified person under National Instrument 43-101, has reviewed and approved the technical content of the announcement. This disclosure indicates that technical statements in the release have undergone qualified professional review.
Timeline and Conditional Production Commencement
The company indicated that activities to commence gold production this year are on schedule with only modest delays to date as of July 16, 2026. The sequential timeline envisions camp assembly (3–4 weeks), mill pad clearing and road construction (2 weeks), mill assembly (9–13 weeks), mill feed extraction (commencing one week before mill start-up), and full operations commencement. Each phase depends on successful completion of prior phases and receipt of necessary regulatory approvals.
Full operations require approvals of all remaining Management Plans. The Water and Groundwater Management Plan is specifically noted as subject to a board directive requiring two years of post-2023 wildfire baseline sampling, which may extend the timeline for final regulatory clearance. Dave Webb, President and CEO, stated that the company is "moving the project forward with full support of the federal, territorial and indigenous governments, subject to the MVLWB regulations" and expressed confidence in meeting current requirements to advance to the next production phases.