Talamore Mining Corp. (TSX: TALA) (OTCQB: TALMF) has marked the first anniversary of its acquisition of the Coffee Gold Project in Yukon, Canada, highlighting a series of major milestones achieved in the past 12 months. The company has assembled a construction financing package of up to C$688 million and secured critical permitting for its access road, positioning the project toward a Final Investment Decision in the first half of 2027. Investors are watching closely as the company advances its Feasibility Study and remaining mine licences ahead of that milestone.
Key Points
- Talamore Mining Corp. (TSX: TALA) (OTCQB: TALMF) marks one year of ownership of the Coffee Gold Project in Yukon
- Construction financing package of up to C$688 million assembled, including a C$450 million secured project debt facility closed October 15, 2026
- Preliminary Economic Assessment outlines an after-tax NPV (5%) of US$2.3 billion and IRR of 47.8%; Feasibility Study expected Q1 2027
- Investors should watch for receipt of the Type A Water Licence, Quartz Mining Licence, and the Final Investment Decision targeted for H1 2027
C$688 Million Financing Package Assembled Ahead of Coffee Gold FID
Talamore has put together a multi-component financing structure totalling up to C$688 million. This comprises a C$149.5 million brokered equity offering closed July 21, 2026, a C$450 million secured project debt facility at a fixed rate of 8.65% over a seven-year term closed October 15, 2026, and potential proceeds of up to C$88 million from a warrant early-exercise incentive program running until November 16, 2026. The debt facility requires no mandatory hedging, offtake, streams, or royalties, preserving shareholders' full exposure to gold prices. Purchasers of the debt facility include Pierre Lassonde and Agnico Eagle.
Access Road Permit Secured and Early Works Advancing Across the 214-Kilometre NAR
The company received its primary Resource Road permit in August 2026, enabling construction of the 214-kilometre all-season Northern Access Route connecting Dawson City to the project site. Road upgrades and new construction are currently underway, with equipment barged to site via the Yukon River during the summer season. A new construction camp and a new airstrip are also advancing, with the airstrip expected to be operational before year-end 2026. These early works are designed to derisk the construction schedule ahead of a potential positive Final Investment Decision.
PEA Economics and Feasibility Study Progress at Coffee Gold Project
A Preliminary Economic Assessment released February 22, 2026, outlined a 13-year open-pit heap leach operation producing an average of 249,000 ounces of gold per year in the first five full years and 217,000 ounces per year over the life of mine. The study returned an after-tax NPV (5%) of US$2.3 billion and an IRR of 47.8% at consensus gold prices. G Mining Services is completing the Feasibility Study, expected in Q1 2027, incorporating infill drilling results from a program that has exceeded 46,000 metres drilled. The PEA is preliminary in nature and there is no certainty its projections will be realised.
Remaining Mine Licences and Regulatory Milestones Before the Construction Decision
Coffee entered Talamore's ownership with a positive 2022 assessment decision under the Yukon Environmental and Socio-economic Assessment Act. The two remaining licences — the Type A Water Licence and the Quartz Mining Licence — are each progressing through final regulatory stages. The public comment period for the Water Licence closed September 15, 2026, with a public hearing to follow. The Quartz Mining Licence is completing its Detailed Information Request stage. Talamore states it expects to receive both licences before its planned Final Investment Decision in the first half of 2027, subject to applicable regulatory processes.