Tocvan Ventures Corp. (CSE: TOC | OTCQB: TCVNF | FSE: TV3) has released a detailed phased development plan for pilot-scale mining operations at its Gran Pilar Gold-Silver Project in Sonora, Mexico, marking the company's formal transition from exploration into near-term production. The plan centres on a fully permitted 50,000-tonne heap-leach facility designed to generate initial cash flow, validate metallurgy at scale, and reduce the technical and financial risk associated with advancing toward commercial production. With heavy equipment already mobilised on-site and construction of the leach pad and containment ponds actively underway, the company is targeting a first gold-silver doré pour in the fourth quarter of 2026. Investors in junior mining and precious metals exploration may be watching the project closely given elevated gold prices and the company's stated intent to use pilot operating data to directly inform a larger commercial development strategy.

Key Points

  • Tocvan Ventures Corp. (CSE: TOC | OTCQB: TCVNF | FSE: TV3) has announced a six-phase development plan for pilot mine operations at its Gran Pilar Gold-Silver Project in Sonora, Mexico.
  • The company is advancing a fully permitted 50,000-tonne heap-leach pilot facility and is targeting its first gold-silver doré pour in Q4 2026.
  • Key permits already secured include a 10-year pilot mine permit obtained in August 2025 and a 6-year Community Agreement executed in May 2026; target gold recovery is stated at 70% via heap-leach; approximately 78.7 million shares are currently outstanding.
  • Investors may be watching for updates on Phase 3 crushing and stacking operations, the commissioning of the Hermosillo-built processing plant, and the company's first production and metallurgical reporting milestone in late Q4 2026.

Gran Pilar Transitions from Exploration to Pilot Production

Tocvan Ventures Corp. announced on July 15, 2026, that it is advancing Gran Pilar from an exploration-stage asset into a pilot-scale producing operation. The company describes this as a pivotal transition, underpinned by the receipt of all major operating permits and significant on-the-ground construction progress. The disclosure represents one of the most operationally detailed updates the company has issued regarding the project, moving beyond resource-level results to describe the specific engineering and infrastructure milestones required before ore can be processed.

The Gran Pilar Gold-Silver Project is located in Sonora, Mexico, a jurisdiction the company characterises as mine-friendly. Tocvan holds a 100% interest in more than 21 square kilometres of prospective ground at the property. The project's exploration track record includes near-surface intercepts of 3.1 metres grading 19.4 grams per tonne gold, and the company has previously reported metallurgical results showing up to 99% gold and 97% silver recovery under certain laboratory conditions. The heap-leach pilot facility, by contrast, targets a more conservative 70% gold recovery at operational scale, which the company notes is a standard benchmark for oxide heap-leach processing.

Permit Security and Community Agreement Provide Operational Foundation

A critical enabler of the pilot programme is the regulatory framework that Tocvan has assembled over the past year. The company secured its 10-year pilot mine permit in August 2025, providing the legal basis to conduct extractive operations at Gran Pilar. This was followed by the execution of a 6-year Community Agreement in May 2026, which the release states provides long-term operational stability and expansion flexibility. The combination of a long-duration mine permit and a multi-year community agreement is designed to reduce permitting and social risk, two of the most significant obstacles junior mining companies face when transitioning from exploration to production in Mexico.

The release does not provide further details on the financial terms of the Community Agreement or the specific community stakeholders involved. However, the disclosure suggests that these agreements are now considered foundational to the project's phased advancement, and their completion ahead of the pilot's construction phases represents a meaningful de-risking milestone for the asset. Investors tracking the project may note that the permit and community agreement together provide a timeframe extending well beyond the pilot phase itself, which the company states is consistent with its intention to use the pilot to inform a broader commercial development strategy.

Infrastructure Construction Status Across the Heap-Leach Facility

According to the announcement, construction of the pilot facility is well underway. Heavy equipment — including a dozer, excavator, and haul truck — was mobilised to site in April 2026. Site preparation activities including fencing, levelling, and groundworks for the heap-leach pad and containment ponds have been completed. The company states that pad and containment pond construction is currently underway, with the base for the containment ponds packed with clay and ready for liner installation. Excavation of the foundation for the heap-leach pad is also described as complete and being prepared for its clay base and liner.

In parallel, the company has contracted local crushing equipment and is constructing the processing plant in Hermosillo, the state capital of Sonora. Condemnation drilling and water monitoring wells have been completed, and baseline environmental data collection is described as ongoing. Active trenching of at-surface oxide gold-silver material across expansion targets is also currently underway. The release includes a plan-view layout map of the pilot facility and photographs documenting construction progress, providing investors with visual evidence of on-the-ground advancement. The 1.76-hectare engineered heap-leach pad is the central infrastructure component of the facility.

Phase 1 and Phase 2: Stockpiling Material and Building the Leach Pad

The company's six-phase plan begins with two concurrent and ongoing phases targeting completion in Q3 2026. Phase 1 involves trenching and material transport, with the objective of securing and characterising 50,000 tonnes of high-grade oxide feed material. Key activities include expanding dozer trenching across South Block high-priority targets and hauling and stockpiling mineralised material. The stated milestone for this phase is the stockpiling of 50,000 tonnes of feed material.

Phase 2 runs concurrently and involves the construction of the engineered 1.76-hectare heap-leach pad and its associated containment system. Activities described include site grading, compaction, impermeable liner installation, solution collection pipe placement, construction of containment berms, and the installation of emergency ponds. The milestone for Phase 2 is the certification of the pad as ready for ore stacking, with full environmental sign-off. The release does not disclose the specific cost of constructing the pad or the total capital expenditure associated with the pilot facility as a whole. The company did not disclose this figure in the announcement.

Phase 3 and Phase 4: Crushing, Stacking, and Processing Plant Commissioning

Phase 3, described as upcoming and targeted for Q3 2026, involves crushing mined material to an optimal size and stacking it onto the heap-leach pad in lifts of four to six metres. The stated milestone is having 50,000 tonnes of ore fully stacked and preconditioned for leaching. The company has already contracted local crushing equipment, which the release indicates is a logistical step that supports the Q3 timeline for this phase.

Phase 4 is described as running concurrently with Phases 2 and 3, also targeting completion in Q3 2026. Its objective is the commissioning of the hydrometallurgical processing plant. Key activities include the installation of a five-column carbon-adsorption circuit, solution ponds, and pumps. The milestone for this phase is the plant being fully commissioned and dry-tested. The processing plant itself is being constructed in Hermosillo, and the release notes it will be transported to site as part of the facility build. No specific equipment cost or installation timeline beyond Q3 2026 is provided in the announcement.

Phase 5: Heap-Leach Processing and Real-Time Recovery Monitoring

Phase 5 covers the actual extraction of gold and silver at pilot scale and is scheduled to span Q3 through Q4 2026. During this phase, a dilute sodium cyanide solution will be applied via drip irrigation across the stacked ore over a leach cycle estimated at 60 to 90 days. The pregnant solution will recirculate through the system, with dissolved metals adsorbed onto activated carbon via the five-column circuit installed in Phase 4. Recovery rates will be monitored in real time throughout the leach cycle.

The stated milestone for Phase 5 is achieving a target of greater than 70% overall gold recovery, as well as the collection of detailed metallurgical and cost data. This data is described in the release as having direct utility for informing the company's commercial development strategy — specifically for evaluating the economics and design of a potential Phase 2 expansion. The 60-to-90-day leach cycle duration means that if stacking commences on schedule in Q3 2026, processing results could begin to emerge in the October-to-December 2026 window, consistent with the company's Q4 2026 doré pour target.

Phase 6: First Doré Pour and Financial Reporting in Late Q4 2026

The final phase of the pilot plan, Phase 6, targets the production and reporting of the first gold-silver doré in late Q4 2026. Key activities described in the release include weighing and assaying the first pour, securing the material, and preparing a cash-flow analysis and report. The company also states it will evaluate all-in sustaining cost (AISC) data and optimisation results as inputs into planning for a potential Phase 2 commercial expansion.

The release frames the first doré pour as both an operational and financial milestone, noting that it is intended to generate initial revenue at a time of what it characterises as current high gold prices. CEO Brodie Sutherland is quoted in the release stating: "This pilot operation is the first step toward establishing Gran Pilar as a scalable, long-life gold-silver producer. With construction progressing, equipment on site, and processing infrastructure being built, we remain firmly on track for our first gold-silver doré pour in Q4 2026. The operating data and cash flow generated will directly inform our commercial development strategy." The company has not disclosed projected revenue figures or doré production volumes for the pilot phase. The company did not disclose these figures in the announcement.

Gran Pilar's Resource Base and Picacho Project Context

Gran Pilar is described in the release as Tocvan's flagship asset. The company holds a 100% interest in more than 21 square kilometres of ground at the project, with the land position expanded through a pivotal 2023 acquisition that the company states provides ample space for scalable mine infrastructure. Exploration results at the property include near-surface high-grade intercepts of 3.1 metres at 19.4 grams per tonne gold. Metallurgical testing has returned results of up to 99% gold and 97% silver recovery, though the release notes these are laboratory results and the heap-leach pilot targets a more operationally realistic 70% gold recovery.

The company also holds a 100% interest in the Picacho Gold-Silver Project, located in the Caborca Trend in Sonora. The Caborca Trend is described in the release as home to some of Mexico's largest gold deposits. Picacho is presented as a growth asset complementary to the near-term pilot production focus at Gran Pilar. The release does not provide updated resource estimates, drilling results, or development timelines for Picacho in this announcement. Investors interested in Picacho's status may need to refer to prior disclosures. Tocvan's total shares outstanding are approximately 78.7 million, as stated in the release.

Technical Oversight and Qualified Person Sign-Off

The technical information contained in the announcement has been reviewed and approved by Brodie A. Sutherland, CEO of Tocvan Ventures Corp., who is identified as a Qualified Person (QP) as defined by Canadian National Instrument 43-101. This designation is a standard requirement under Canadian securities regulations for the disclosure of scientific and technical information related to mineral projects, and the sign-off is intended to provide investors with assurance regarding the accuracy and appropriateness of the technical content disclosed.

The QP's dual role as both the company's CEO and the technical approver of the disclosure is a common arrangement among junior mining companies, where executive leadership frequently holds professional geological qualifications. The release does not identify any independent QP review of the technical data, which is not uncommon at the pilot development stage but is a factor investors may wish to consider when assessing the technical claims made in the announcement. The immediate share price impact was not clear from available public information at the time of publication.

Sonora Jurisdiction and the Broader Gold Market Context

Tocvan has consistently positioned Sonora, Mexico, as a favourable jurisdiction for gold and silver mining development. The state has an established history of mining activity and is home to a number of significant producing operations. The company characterises the jurisdiction as mine-friendly, citing the ability to obtain a 10-year pilot mine permit and a multi-year community agreement as evidence of regulatory and social support for the project's advancement.

The release references a strong gold market and record-high gold prices as a positive external backdrop for advancing the pilot facility toward first production. While the announcement does not cite specific gold price levels, the reference to current market conditions frames the Q4 2026 first pour milestone as potentially advantageous from a revenue timing perspective. Investors should note, however, that gold prices are subject to significant volatility, and the company makes no specific revenue projections or economic guarantees in this disclosure. All forward-looking statements are subject to the risks and uncertainties identified in the cautionary language included in the release.