Western Exploration Inc. (TSXV: WEX | OTCQX: WEXPF) has submitted its Mine Plan of Operations to the United States Forest Service for its 100%-owned Doby George gold project in northeastern Nevada, formally initiating the federal permitting process. The submission, announced August 5, 2026, follows a multi-agency site visit on July 7, 2026, during which USFS representatives reviewed the proposed project layout. The milestone marks a significant step for the company as it advances the project from the assessment stage toward a potential permitted mine.
Key Points
- Western Exploration Inc. (TSXV: WEX | OTCQX: WEXPF) announced submission of its Mine Plan of Operations (MPO) to the USFS
- The MPO initiates formal federal review, including an environmental review process under the National Environmental Policy Act
- The project contemplates a 7,500 tonne/day open-pit, heap-leach gold mine with a total disturbance of 697 acres (282 hectares)
- Investors may be watching progress on the parallel pre-feasibility study and the grid power feasibility study results expected in Q4 2026
Doby George MPO Outlines Open-Pit Heap-Leach Design Consistent With 2025 PEA
The MPO describes a 7,500 tonne/day (approximately 8,300 ton/day) open-pit, heap-leach gold operation consistent with the company's 2025 Preliminary Economic Assessment. The project contemplates a total disturbance of 697 acres (282 hectares), of which 345 acres (140 hectares) are on private land available under an existing mineral lease agreement. The remainder falls on federal land administered by the USFS, which is acting as lead agency in the review. The MPO covers surface use, construction, and operation across both federal and private land components of the Doby George project in Elko County, Nevada.
Broad Baseline Environmental Studies Underpin the MPO Submission
Supporting the MPO is an extensive baseline environmental programme that began in February 2026, covering biological resources, cultural and paleontological resources, air quality, hydrogeology, geochemistry, noise, and aquatic resources. Completed work includes raptor surveys, a Class 1 desktop cultural resources review, a desktop paleontological review submitted to the USFS, baseline noise monitoring, and a hydrogeology data review. Ongoing work includes Phase I hydrogeologic investigation scheduled for summer 2026, aquatic resource surveys, and multiple biological surveys targeting species such as greater sage-grouse, American goshawk, and pygmy rabbit, among others.
Pre-Feasibility Study and Grid Power Assessment Advancing in Parallel
Western Exploration states it is continuing hydrogeological test work and a drill programme announced on July 28, 2026, both designed to support a planned pre-feasibility study (PFS) for Doby George. A grid power feasibility study being completed by Raft River Rural Electric Cooperative Inc., announced in June 2026, remains in progress. The company disclosed that results from that study are expected in the fourth quarter of 2026 and will form part of the PFS. The scientific and technical content of the announcement was reviewed and approved by Mark Hawksworth, P.Geo., General Manager of Western's Aura Project, as a qualified person under NI 43-101.