Key Highlights

  • Fermi shares closed 13.81% higher on Thursday, November 12, 2026, after reaching as high as 19.89% during the session.
  • The company disclosed arrangements with an undisclosed investment-grade hyperscaler for an opening 600 MW at Project Matador, starting in 2027, featuring a USD 200 million prepayment.
  • No definitive Lease has been executed yet, and the earlier TensorWave lease covering 222 MW was ended.
  • Third quarter net loss totalled USD 141.6 million, and the company still has no revenue.

Terms of the Hyperscale Agreements

Fermi is building a large power and Data Center campus named Project Matador. On Thursday it announced agreements with an investment-grade hyperscale customer, which it did not identify, to advance an initial 600 MW of capacity beginning in 2027. The arrangement includes a USD 200 million prepayment, an early construction and site development contract worth USD 15 million, and a USD 90 million order for structural steel and building materials that is still being finalized. The parties are moving toward a definitive long-term lease, and conditions attached to the Texas Tech land lease must be satisfied before vertical construction begins. Fermi (NASDAQ:FRMI) traded as high as 19.89% during the session and closed 13.81% higher. The prepayment matters most, because it supplies customer funding for a project that requires heavy capital. Big tech buyers have been chasing locations with access to electricity, the chief limit on building new AI facilities, which makes a customer pledge at a power-rich property meaningful. Traders who booked gains explain the distance between the session high of 19.89% and the 13.81% finish.

Financials Show the Cost of a Pre-Revenue Build

Fermi has no revenue, and the third quarter illustrated what construction costs. Per share, the loss amounted to USD 0.22, which came to USD 141.6 million in total, against USD 346.8 million a year earlier. Of the USD 142.2 million in general and administrative costs, USD 65.8 million was non-cash Stock Compensation and USD 21.5 million reflected advisory fees paid in shares. The company invested USD 133.4 million in property and equipment during the quarter and USD 759.5 million over nine months. The Debt balance, net of costs, reached USD 958.4 million, compared with USD 109.8 million at the close of 2025, while total cash and restricted cash came to USD 315.5 million. Fermi also brought to a close the TensorWave arrangement, a data center lease and services contract from August together with its linked Credit support pact, which cleared away an earlier customer obligation. The stock-based charges are non-cash but dilute holders, and the larger debt load will lift interest costs as construction proceeds. The company's own description as pre-revenue and pre-lease highlights that its biggest value drivers still lie ahead.

Lease Conversion, Customer Identity and Financing

A customer rated Investment grade that pays in advance cuts financing risk, which helps explain the jump. Even so, the deal is not a signed lease, the prepayment depends on conditions and meaningful Revenue lies years away. The company indicates that, should binding customer deals follow, the project could expand toward roughly 17 GW, a sizeable number that hinges on permits, power access and financing. Management has indicated that converting its pipeline would Fill the 2.2 GW of capacity it has at present. Watch items include the signing of the binding lease, who the customer is, how construction gets funded and how power development proceeds. Given its debt and cash burn, any slippage could weigh on the shares fast. Risks include construction cost overruns, equipment delivery schedules and the possibility the customer alters its plans, which is why lease terms matter so much. Borrowing costs for a developer funding heavy construction are pushed up by the 10-year Treasury yield, which sits near 5.10%.

Where Things Stand

Fermi (NASDAQ:FRMI) secured a hyperscale customer pledge covering 600 MW and a USD 200 million prepayment, though no firm lease is yet signed. Lease execution, construction financing and permits are the next milestones. With the company still pre-revenue and its debt rising, execution is the central risk.