A second Wyoming site joins the hub
What Ur-Energy Inc. (TSX:URE) is building in Wyoming is a hub-and-spoke uranium production network, and the second-quarter update made 2026 the year the second spoke began to turn. The company's Shirley Basin project has received final state authorisation for full production, started limited operations in April and had its infrastructure for trucking uranium-loaded resin to the Lost Creek processing plant in place by the end of July. Lost Creek, meanwhile, recorded its highest quarterly drummed output since ramp-up began in 2022. The developments matter because they determine how much of the company's licensed capacity can actually be converted into delivered pounds under its sales contracts.
Ur-Energy describes itself as an in-situ recovery (ISR) uranium miner. ISR operations pump a leaching solution through underground ore bodies and recover dissolved uranium at surface, avoiding conventional open-pit or underground mining. The company is headquartered in Casper, Wyoming, and reports in US dollars.
Listings
The shares are listed on the Toronto Stock Exchange under URE and on the NYSE American under URG.
Second-quarter operations and sales
Results for the three months to 30 June 2026 were released on 10 August 2026. Ur-Energy sold 215,000 pounds of U3O8, all under long-term contracts, generating product sales of US$14.4 million. The average realised price was US$66.85 per pound, below the US$70.98 achieved in the first quarter but above US$63.20 a year earlier. Cash cost per pound sold, which includes ad valorem and severance taxes, was US$40.20, compared with US$37.51 in the previous quarter. The company reported product profit of about US$2.0 million for the quarter, equivalent to US$9.53 per pound. The release referred investors to the quarterly Form 10-Q for the full income statement, and this article does not cite a net result.
At Lost Creek, 105,016 pounds were captured in the quarter, slightly down on the first quarter, while 140,873 pounds were drummed, a record since the 2022 ramp-up, and 149,747 pounds were shipped. Cumulative production has passed 3.5 million pounds. Seventeen drill rigs were working at quarter-end, and a sand filtration system was installed during the quarter and brought online in July. Shirley Basin contributed 10,634 captured pounds in its first partial quarter. The site is designed as a satellite of Lost Creek rather than a standalone processing plant.
Cash, contracts and the absence of a dividend
Unrestricted cash and equivalents were US$95.3 million at 30 June, down from US$122.8 million at the end of March, reflecting continued spending on wellfield development, construction and exploration. The release did not set out debt or share-count details. Ur-Energy does not pay a dividend, consistent with the company's practice of reinvesting cash into development.
The contract book is central to the investment case. The company expects to deliver 1.0 million pounds of base contract volumes in 2026, of which 270,000 pounds were delivered in the first half. After the quarter, it agreed deferrals of 150,000 pounds into 2027 and a further 150,000 pounds into 2029. Finished inventory held at the conversion facility was 348,292 pounds at the end of June, although a separate inventory table in the release showed a different total, so readers may wish to consult the 10-Q for reconciliation. Combined licensed production and toll-processing capacity across Lost Creek and Shirley Basin is 4.2 million pounds a year.
Development pipeline
Several projects are scheduled over the coming quarters. Construction of wellfields in a fifth mine unit at Lost Creek is expected by the end of 2026, subject to regulatory approval, with 15 header houses planned from late 2026 through 2028. Ground was broken on a Lost Creek wastewater treatment facility in July, with completion targeted for the first quarter of 2027. At Lost Creek South, a roughly 16-square-mile area next to the existing operation, a 120-hole drilling programme using three rigs was expected to begin in the third quarter. At Lost Soldier, where around 4,000 historic holes exist, aquifer pump testing has been carried out and a technical report with a resource estimate is expected by the end of 2026.
Market backdrop
Ur-Energy sells into the nuclear fuel market, where utilities typically buy under multi-year contracts rather than on the spot market. Interest in domestic US supply has been supported by energy-security policy, reactor life extensions and growing electricity demand forecasts, including from data centres. These factors have encouraged utilities to secure long-term supply, which benefits producers with operating plants. At the same time, uranium prices are volatile, and the company's realised price depends on the mix of fixed and market-related pricing in its contracts. The modest fall in realised price in the second quarter illustrates that contracted revenue does not move in step with headline price indicators.
Risks and milestones
The principal operating risk is execution. ISR wellfields can underperform expectations, and Lost Creek's captured pounds slipped in the quarter even as drumming rose, which shows that plant throughput and wellfield recovery do not always move together. Shirley Basin is newly operating, and its economics will depend on achieving steady flow rates and reliable resin transport. Rising cash costs, regulatory timelines for new mine units, contract deferrals and uranium price volatility all affect margins. The decline in cash during the quarter highlights that development spending continues to exceed product profit, so funding needs and any future equity issuance remain relevant considerations.
Disclosed milestones to watch include the first resin shipments from Shirley Basin to Lost Creek, third-quarter results, the start of fifth mine unit wellfield construction, the Lost Soldier technical report and progress on the wastewater facility. Those updates will show whether production growth is translating into deliveries and margins at the scale management has outlined.