Pulsar Helium is targeting first helium production from its Topaz project in northern Minnesota in the fourth quarter of 2027, according to the company's project page. To get there, it plans to drill up to six additional production wells between the first and second quarters of 2027, complete processing and liquefaction infrastructure, and secure permits under a new Minnesota framework for helium development. The timeline is a company target rather than a commitment, and it depends on financing, permitting and construction.

What Topaz is

Topaz is a primary helium discovery in Lake County, Minnesota, about 65 miles north of Duluth. Unlike most of the world's helium, which is produced as a by-product of natural gas, Topaz contains helium that occurs independently of hydrocarbons. Pulsar (TSXV:PLSR) owns the project outright. Flow testing showed the Jetstream #1 well averaging 8.1% helium and Jetstream #2 averaging 5.6%, concentrations that are exceptionally high by industry standards. Jetstream #1 has flowed more than 1.3 million cubic feet per day under well-head compression.

Two US federal laboratories, the US Geological Survey Noble Gas Laboratory and Lawrence Livermore National Laboratory, have independently confirmed helium-3 concentrations of about 11.2 to 11.9 parts per billion in raw gas from Jetstream #1. Helium-3 is a rare isotope used in quantum computing, security and research, and Pulsar has signed an evaluation agreement with Lunar Helium-3 Mining to test whether it can be recovered economically.

Progress through 2026

Between October 2025 and March 2026, Pulsar drilled five core-hole appraisal wells at Topaz, all of which encountered gas under high pressure. Two wells are considered production-ready. In May 2026, Minnesota Governor Tim Walz signed legislation creating helium-specific permitting guidelines, and the state Department of Natural Resources proposed expedited permitting rules on May 18. Pulsar also acquired about 1,360 acres of surface land over its leased mineral rights at Topaz, giving it greater control over development.

In July, Pulsar entered a binding agreement to reserve a helium liquefaction plant and equipment package valued at about US$78.7 million. The company said the reservation could strengthen its route to market and potentially allow earlier Revenue from processing third-party gas while it advances permitting. It is working with Chart Industries on design of an integrated helium production and carbon dioxide capture solution.

The financial picture

Pulsar has no revenue yet. Its net loss widened to about US$7.1 million in the quarter ended June 30, 2026, as exploration spending rose, and its net loss for the nine months to June 30 was about US$19.4 million, compared with US$8.5 million a year earlier. It raised funds during 2026, including about US$16.1 million reported for the first half of its fiscal year, to accelerate the move from appraisal to production planning. Its fiscal year ends September 30, so annual results for fiscal 2026 are expected in the coming months.

Why the timing matters

The global helium market has tightened sharply in 2026. The closure of Qatar's Ras Laffan LNG production in March removed roughly a third of global helium supply, and QatarEnergy's partial restart has run at about a quarter of normal capacity. Russian export controls have reduced Supply further. A new North American source of high-grade primary helium could command strong pricing, which helps explain investor interest in Topaz.

How Pulsar compares with other helium developers

Pulsar is one of a small number of listed companies trying to develop new helium supply in North America, alongside explorers in Saskatchewan, Alberta and the western United States. Many of those projects target helium mixed with nitrogen or carbon dioxide at concentrations of around 1%, which require significant processing. Topaz's grades of 5% to more than 8% are well above that level, which could translate into lower processing costs per unit of helium if flow rates hold up in production. The project's location in a state without an oil and gas industry, however, means that regulation, infrastructure and local services have had to be built largely from scratch, which can add time.

Possible timeline conflicts

Earlier company commentary suggested drilling of production-ready wells could begin in September 2026, while the current project page targets new well drilling in the first half of 2027. Any slippage in drilling, permitting or plant delivery could push first production beyond the fourth quarter of 2027.

Key risks

Pulsar faces typical development-stage risks: it needs substantial Capital to build wells, processing and liquefaction facilities, which could require more Equity and dilute shareholders. Permitting under Minnesota's new framework has not yet been tested for a commercial project. Resource estimates may change as more data is collected. Helium prices could fall if Qatari supply recovers faster than expected. Construction delays and cost overruns are common in new energy projects.

What to watch next

Key milestones include an independent resource update and economic assessment, confirmation of the production well drilling schedule, permit applications and approvals, financing announcements, offtake agreements with helium buyers, and results from the helium-3 evaluation. Fiscal 2026 annual financial statements will also update the company's cash position.

Conclusion

Pulsar Helium is aiming for first helium from Topaz in the fourth quarter of 2027, supported by high helium grades, new Minnesota permitting legislation, a reserved liquefaction plant and a tight global helium market. The company still needs to drill production wells, finance and build infrastructure and secure permits, so the timeline should be treated as a target. For investors, TSXV:PLSR remains a pre-revenue development story with significant upside potential and corresponding risk.