Pulsar Helium's (TSXV:PLSR) next major payment under its equipment agreement with Chart Energy & Chemicals is US$8.55 million, due by January 31, 2027. That payment authorizes Chart, now part of Baker Hughes, to begin buying long-lead items for a helium liquefaction plant and a carbon dioxide (CO2) plant planned for Minnesota. If Pulsar does not pay by that date, the contract does not end; the project instead enters a suspension of up to 180 days, during which reserved equipment stays protected and no cancellation charge arises solely from the pause. For shareholders of TSXV:PLSR, the January deadline is effectively the first financing test of the company's plan to move from helium discovery to processing.
The Chart Proposal in Detail
Pulsar announced on October 1 that its subsidiary, Pulsar Helium MN Inc., had signed and accepted a firm proposal from Chart Energy & Chemicals, a wholly owned Subsidiary of Baker Hughes following its July 2026 Acquisition of Chart Industries. The aggregate equipment-supply price is US$85.5 million for a helium purification and liquefaction plant and a CO2 plant. The company was explicit that this is not the total installed cost: taxes, duties, tariffs, installation, commissioning and site infrastructure are excluded.
The helium plant is designed for 861 litres per hour, or about 7.5 million litres of liquid helium a year at continuous nameplate operation, equivalent to roughly 200 million standard cubic feet of gaseous helium. The CO2 plant is sized at 300 tonnes a day of capture capacity. Payments are staged. A first payment of US$5.025 million is due on signing and TSX Venture Exchange approval, including US$750,000 already paid under a limited notice to proceed. The US$8.55 million second milestone follows by January 31, and the balance, about US$71.9 million by simple subtraction, is tied to engineering, procurement, Manufacturing and delivery milestones. Chart expects manufacture to take about two years after the second payment. If Pulsar later terminates for convenience, cancellation charges escalate from zero at award to a maximum of 70 per cent of contract value.
How Much Cash Pulsar Has
At the time of the announcement, Pulsar said it had cash resources of US$25.2 million and would fund the first payment from existing cash. An October 12 report cited unaudited cash of about US$24.6 million. That balance reflects a US$25.5 million private Placement completed after June. On paper, Pulsar can cover the first two milestones from cash on hand, but doing so would absorb a significant share of its treasury while it also funds drilling, permitting, engineering and corporate costs. In its quarter ended June 30, the third quarter of its fiscal year, Pulsar reported a pre-tax loss of US$7.1 million, up from US$1.4 million a year earlier, as spending at Topaz increased.
The company has said it "continues to advance financing alternatives" for the remaining payments and wider development costs. Pulsar is in discussions, not agreements, with University Bank, whose parent University Bancorp is a Pulsar shareholder, as well as Minnesota's Department of Employment and Economic Development, the state's Iron Range Resources and Rehabilitation agency, and the U.S. Department of Agriculture's Rural Development guaranteed Loan program. Any public support would be subject to formal review and approval.
The Two Harbors Site and Minnesota Approvals
The plants would sit at a proposed Rare Gas Hub in Two Harbors, Minnesota, on Lake Superior. On October 15 Pulsar said the city council had approved a purchase and development agreement for land in an existing industrial district, at a purchase price of US$1.00 against an appraised value of US$143,200. The city would contribute up to US$1 million toward rail construction and reimburse 90 per cent of the increased city share of property taxes for 15 years once the initial phase operates commercially. The site has access to Canadian National Railway's main line, deep-water port facilities and highways.
The agreement starts a 365-day Due Diligence period from October 14. Pulsar can walk away before delivering a project commitment notice; once it commits, the initial phase must reach commercial operation within 36 months, subject to permitted extensions. Closing also depends on financing, environmental review, zoning and Utility arrangements. Separately, the regulatory approvals needed for helium production at Topaz remain outstanding.
What Supports the Plan
Pulsar's Topaz project has produced encouraging data. Seven wells have encountered pressurized gas containing helium, and the Jetstream #1 discovery well tested up to 14.5 per cent helium-4, with an average flow-test concentration of 8.1 per cent. Policy has also moved in its favour: on October 23 the U.S. Department of Energy designated helium a critical material. Pulsar's Leadership changed on October 30, with president Cliff Cain becoming CEO and Thomas Abraham-James moving to executive chair, and Canaccord Genuity was appointed sole broker.
The resource base, however, is still early-stage. Sproule's October 2024 independent assessment estimated a P50 gross recoverable prospective helium-4 resource of 0.4 billion cubic feet, based only on Jetstream #1 before it was deepened. Prospective resources are not reserves, and Pulsar has not yet published an economic or feasibility study supporting the Rare Gas Hub; its own disclosure lists the absence of such a study as a risk. A feasibility study has been described as a 2027 milestone.
Risks and the Road to January
The key risks are financing, cost and timing. Pulsar is committing to equipment before it has a feasibility study, reserves, production permits or binding project finance. Installed costs will exceed the US$85.5 million equipment price. Delays in TSXV approval, permitting or lender decisions could push the schedule, and any Equity raise could dilute existing holders. Helium and CO2 prices, and the cost of the Chart milestones in U.S. dollars, add further uncertainty for a company that also trades on London's AIM market under PLSR and on the OTCQB as PSRHF.
Between now and January 31, investors are likely to watch for TSXV approval of the Chart agreement, Pulsar's fiscal 2026 annual financial statements, which cover the year ended September 30, any binding Debt or grant commitments, and an updated resource estimate incorporating the newer wells. The suspension clause gives Pulsar some flexibility if money is slow to arrive, but it does not remove the need to fund a project that remains well ahead of its technical studies.