Europe wants more of its own natural gas, and a small Calgary-based company is trying to deliver some from southern Poland. On Friday, Horizon Petroleum (TSXV:HPL) announced that production testing had begun at its Lachowice 7 well, and that gas was flowing on its own at an early rate the company called encouraging.
What happened at Lachowice 7
The Lachowice 7 well, known as L7, is in the Bielsko-Biala concession in southern Poland. It is operated by Energia Karpaty Zachodnie, Horizon's wholly owned Polish subsidiary.
The well began flowing naturally at about 6:30 a.m. local time on September 25, 2026. Early results showed:
A flow rate of 5.5 million cubic feet of Natural Gas per day.
Wellhead pressure of about 2,500 PSI.
A choke size of 28/64 of an inch, which controls how fast gas flows from the well.
The company stressed that the well is still in its cleanup phase, so these rates are preliminary and could change.
A well with a history
L7 is not a new discovery. Previous operators tested it decades ago. In 1994, it reached a peak rate of 8.9 million cubic feet per day. In 1999, it flowed at about 3.0 million cubic feet per day for two weeks.
Horizon's early rate sits between those historical results, which is a promising start for a well that has been re-entered and worked over.
The work behind the flow
Before testing, Horizon completed an acid stimulation treatment, a common technique that helps gas flow more easily through rock. It also used a coiled tubing unit to unload fluids from the well.
One complication: a significant Volume of water was lost into the formation during the mechanical workover. Recovering that water is ongoing, and it may affect flow rates during the cleanup phase.
What comes next in testing
Horizon (TSXV:HPL) laid out a clear plan. The cleanup phase is expected to last 24 to 36 hours of variable-rate flow. After that, the well will be shut in so pressure can build up, and the company will run production logging to see exactly where gas is entering the wellbore. Then a main flow and pressure build-up testing program will follow.
That sequence matters because a short flow test only shows part of the picture. Longer tests reveal how much gas the reservoir can deliver over time, which is what determines whether a well is commercially valuable.
Why this matters
Management said: "The Company considers these initial results encouraging; however, the well remains in the cleanup phase." That is a measured way to put it, and investors should read it the same way.
The bigger picture is that Europe has been looking for secure, local gas supplies. A producing well in Poland could find a ready market, and success at L7 could support further development in the Bielsko-Biala concession.
For a small company like Horizon, one well can make a big difference. Re-entering and reworking an existing well is far cheaper than drilling a new one, so if L7 can hold a commercial rate, it could provide Cash Flow relatively quickly and help fund work on other targets in the concession. Proving the reservoir can deliver steady gas would also make it easier to attract partners or financing for the next phase.
What to watch next
Watch for results after the cleanup phase, the pressure build-up data and the production logging results. Those will tell investors whether L7 can sustain meaningful gas production. Plans for bringing the well into commercial production, including connections to local infrastructure, will be the next milestone.