Highlights

  • Carapal Ridge-3 marks the first drilling activity in the pool after 17 years.
  • The well intersected extensive hydrocarbon-bearing Herrera sands across multiple intervals.
  • Completion activities are ongoing, with facility tie-in planned for Q1 2026.

Touchstone Exploration Inc (TSX:TXP) has released an operational update on the Carapal Ridge-3 (“CR-3”) development well, situated on the Central block onshore in the Republic of Trinidad and Tobago. The company holds a 65% operating working interest in the well, while Heritage Petroleum Company Limited owns the remaining 35%.

Drilling Timeline and Execution
The CR-3 well was spud on November 23, 2025, using the Star Valley Drilling Rig #205. Drilling operations were completed over a 35-day period, reaching a total depth of 8,200 feet. Following open-hole logging, the well was cased for future production. Based on preliminary field-level estimates, the well was approximately 25% over budget. No sidetrack operations were required, with additional time and costs mainly attributed to controlling natural gas flows from Karamat sands not previously produced on the Central block.

Reservoir Targets and Geological Findings
The primary objective of CR-3 was the Herrera sands within the Carapal Ridge pool. The well encountered approximately 1,082 feet of net sand, including around 1,000 feet of net Herrera sand. Of this, about 635 feet of net sand was identified in the developed Herrera reservoir above a 30-foot shale marker, while approximately 365 feet of net Herrera sand was encountered below the marker in an unproduced interval. Drilling concluded while still within clean sand at total depth.

In addition, the well intersected approximately 82 feet of net Karamat sands above the Herrera formation at depths between 6,530 feet and 6,760 feet. These sands were also identified in earlier Carapal Ridge wells.

Well Design and Data Interpretation
Although initially planned as a deviated well, CR-3 naturally built angle during drilling, resulting in approximately 341 feet of horizontal drilling within the unproduced Herrera sand package. Open-hole wireline logging, mud logging, and drilling data indicate hydrocarbon-bearing sands throughout the Herrera interval, including the horizontal section.

Completion and Development Outlook
Completion operations are currently underway. Initial production is planned from the lower horizontal Herrera sands below the shale marker, with the option to perforate uphole developed sands at a later stage. Much of the required tie-in equipment has been procured and delivered to Trinidad, with connection to the Central block natural gas processing facility targeted for the first quarter of 2026. The results also support the potential for up to three additional Herrera development wells on the Central block and highlight a secondary gas-charged play in the Karamat formation under evaluation.