Key Highlights

  • Third-quarter 2026 Revenue at CIFR dropped to $26.7 million from a year-earlier $71.7 million.
  • Net income reversed from a $3.3 million loss a year earlier to $31.6 million in the latest quarter.
  • High-performance computing Lease revenue hit $5.9 million, a first for the company.
  • The Sep 30, 2026 Balance Sheet showed $656.0 million in cash and cash equivalents.
  • Management puts contracted revenue for the three HPC campuses at roughly $16.6 billion in total.

Non-Cash Warrant Gain Converts an Operating Deficit Into a Profit

Cipher Digital (NASDAQ:CIFR) published third-quarter numbers on Nov 2, 2026, covering the three months through Sep 30, 2026. Total revenue fell to $26.7 million from $71.7 million in the comparable 2025 quarter. Net Income reached $31.6 million, a turnaround from a $3.3 million net loss a year earlier.

Profit did not originate in operations. The operating loss widened to $71.9 million from $37.6 million a year earlier. A non-cash warrant Liability gain of $127.2 million, plus $32.7 million of interest income, exceeded $59.0 million of interest expense.

Basic earnings per share came to $0.08, but diluted results showed a $0.22 loss per share, since the warrant gain is excluded from the diluted math.

Mining Income Contracts While Black Pearl Begins Generating Lease Payments

The company constructs and manages large data centers dedicated to HPC workloads and continues to mine Bitcoin at a single site in Texas. Bitcoin Mining sales decreased to $20.8 million, down from $71.7 million. Mining at the Black Pearl campus was discontinued in February 2026 when the location shifted to HPC operations.

HPC lease income reached $5.9 million, of which $5.2 million came from fixed rent, once the initial Black Pearl phase became operational in August 2026. At the tenant's request, capacity was handed over earlier than scheduled, and so far 18 MW of critical IT load has been turned over.

Employee compensation and benefits climbed from $14.4 million to $38.6 million, while Depreciation and amortization shrank from $59.5 million to $18.8 million.

September Barber Lake Amendment Raises Contracted Value to About $9.1 Billion

A September 2026 amendment set the Barber Lake lease at 20 years. According to management, contracted revenue at that location climbed to approximately $9.1 billion, which contributes around $5.2 billion of rent. Data halls should be handed over from the fourth quarter of 2026 running into the first quarter of 2027.

Responsibility for the first $359.3 million above the original budget sits with the company, and the tenant covers half of any further overage across the lease. Management stated the average Yield on cost is back to around 15%.

Taken together, the three campuses span 700 gross megawatts, and management put contracted revenue near $16.6 billion with a weighted average lease length of 17.3 years.

Operating Cash Burn, Newly Issued Convertible Debt and Upcoming Deliveries

The nine-month operating cash outflow reached $283.2 million. As of Sep 30, 2026, the cash balance was $656.0 million, while the accumulated deficit stood at $1,353.9 million.

Following the quarter, on Oct 16, 2026, $850.0 million of Zero-Coupon Convertible notes due 2032 were placed. In the same window, about $165.9 million of legacy convertible notes were traded for close to 40.7 million shares. Items to watch: Barber Lake hall handovers extending into early 2027, more Black Pearl phases, and the final Texas load classification for the 1 GW Colchis site, due in December.