- Goose Mine in Nunavut reaches commercial production as of October 2, 2025.
- Mill averaged 66% of design capacity during the initial 30-day commercial period.
- Gold output at Goose Mine projected to total 250,000 oz in 2026.
B2Gold Corp. (TSX:BTO) confirmed that its Goose Mine, located in the Back River Gold District in Nunavut, Canada, achieved commercial production on October 2, 2025. The milestone was based on 30 consecutive days of mill throughput at or above 65% of the mill’s 4,000 tonnes per day (tpd) design capacity.
During the period from September 3 to October 2, 2025, the mill averaged 2,652 tpd, equating to 66% of design capacity, with feed primarily sourced from the mined-out Echo open pit. The integration of a supplemental mobile crusher with the main crushing plant in late September increased ore availability. From September 19 to October 2, 2025, crushing rates reached 183 tonnes per hour, equivalent to approximately 4,385 tpd on a 24-hour basis. Over this same period, mill throughput averaged 3,249 tpd, or 81.2% of design capacity.
Mining Activity and Gold Recovery
Both open pit and underground mining at the Umwelt deposit performed as expected throughout the commercial production period. Mill feed for Q4 2025 will predominantly come from the Umwelt deposit, with anticipated gold grades ranging from 6.5 to 7.0 grams per tonne. Gold recoveries have met initial expectations and are projected to exceed 90% through the remainder of 2025 and beyond.
Clive Johnson, President and CEO of B2Gold, stated, “It is with great pleasure that we announce the Goose Mine has achieved commercial production. This tremendous achievement comes just over three months after the commencement of mill operations. I would like to thank our construction and operations teams, whose tireless efforts have made this entire project possible, and acknowledge our partner, the Kitikmeot Inuit Association, for their longstanding support. The Goose Mine will be a cornerstone of B2Gold’s production base and demonstrates the strength of our construction and operating teams worldwide. We view this milestone as just the beginning for the Back River Gold District and look forward to many years of safe and successful production in Nunavut, Canada.”
Production Guidance
B2Gold confirmed near-term and long-term production estimates for the Goose Mine, forecasting 80,000–110,000 oz in 2025, about 250,000 oz in 2026, and around 330,000 oz in 2027. Average annual production for the first six full years (2026–2031) is projected to be approximately 300,000 oz per year, based solely on existing Mineral Reserves.
About B2Gold
Headquartered in Vancouver, Canada, B2Gold is an international senior gold producer with operating mines in Canada, Mali, Namibia, and the Philippines. The company also manages multiple development and exploration projects globally.






Please wait processing your request...