Highlights
- EPCM Detailed Design for Texas Hub now 25% complete, informing next project steps.
- Advanced GBD techniques included to enable higher coercivity magnets for elevated temperatures.
- UK pilot and Tyseley operations producing magnet samples to support U.S. design and testing.
Mkango Resources Ltd (AIM: MKA, TSX-V: MKA) has provided an update on the engineering, procurement, and construction management (EPCM) Detailed Design phase for HyProMag USA, LLC’s advanced rare earth magnet recycling and manufacturing project in Dallas-Fort Worth, Texas (the “Texas Hub”). PegasusTSI Inc. (U.S.) and BBA USA Inc. (Canada) have been engaged to deliver EPCM services, supporting the development of a domestic supply of neodymium iron boron (NdFeB) permanent magnets for the U.S. market.
The Detailed Design phase is now 25% complete and draws on the technology and design specifications from HyProMag Group’s ongoing commissioning of the Tyseley facility in the UK and the Pforzheim facility in Germany. These designs are being applied to optimize the Texas Hub’s plant design and operating criteria.
Advanced Grain Boundary Diffusion (GBD) techniques have been integrated into the Detailed Design. GBD allows for the production of magnets with higher coercivity (greater than 20 kOe), capable of operating at higher temperatures and offering increased operational flexibility.
In parallel, UK piloting has increased operations, with the University of Birmingham HPMS pilot facility tripling throughput and completing over 50 runs in the last six months. Approximately 900 kilograms of recycled NdFeB alloy powder have been produced at Tyseley Energy Park, with operations progressing toward finished sintered NdFeB magnets. These results are informing engineering design improvements, recoveries, and magnet-making capability for the Texas Hub, while providing samples for further customer testing.
Site selection in Dallas-Fort Worth has identified four short-listed options ranging between 125,000 and 140,000 sq. ft, with commercial discussions ongoing to secure a 25-year lease. Baseline permitting is expected to commence in Q3 2025 once the site is confirmed.
Supply and off-take collaborations are underway, including feedstock stockpiling by Intelligent Lifecycle Solutions (ILS). Additional feed supply providers and potential product off-takers are being engaged concurrently to support project financing requirements.
Mkango is also evaluating expansion, with lead engineers conducting a Scoping Study for additional hubs in Nevada and South Carolina, and a Concept Study by Worley assessing the potential for “Long-loop” recycling processes in the U.S., complementing ongoing pilot work in the UK.
“HyProMag USA has the potential to supply the U.S. market with sustainable, long-term NdFeB magnets,” said Mkango. The company continues discussions with government, commercial lenders, equity providers, and off-takers regarding funding and potential project acceleration.