Highlights 

  • PMET Resources files its NI 43-101 Technical Report for the CV5 lithium-only Feasibility Study. 
  • The report outlines the pathway for a large-scale mining operation at the Shaakichiuwaanaan Project. 
  • The Project hosts one of the largest lithium pegmatite Mineral Resources in the Americas. 
  • The Feasibility Study confirms a maiden Probable Mineral Reserve of 84.3 Mt at 1.26% Li2O. 
  • The Project also contains the world’s largest pollucite-hosted caesium pegmatite resource. 

PMET Resources Inc. (TSX:PMET) has officially filed its NI 43-101 Technical Report for the CV5 Pegmatite lithium-only Feasibility Study on SEDAR+. The report, titled “CV5 Pegmatite Lithium-Only Feasibility Study NI 43-101 Technical Report – Shaakichiuwaanaan Project”, is dated November 14, 2025, with an effective date of October 20, 2025. This filing follows the company’s earlier announcement of a favourable Feasibility Study outlining the potential for a large-scale mining operation at its 100%-owned Shaakichiuwaanaan Project in the Eeyou Istchee James Bay region of Quebec, Canada. 

The report was prepared by G Mining Services Inc. with contributions from several independent consulting groups. 

Resource, Reserve, and Project Scale Reinforce Strategic Importance

The Feasibility Study declared a maiden Probable Mineral Reserve of 84.3 Mt at 1.26% Li2O, based on a cut-off grade of 0.40% Li2O for open-pit and 0.70% Li2O for underground operations. The project is designed to target approximately 800 ktpa of spodumene concentrate through a Dense Media Separation-only flowsheet, reinforcing its potential as a long-life lithium operation. 

PMET’s Consolidated Mineral Resource totals 108.0 Mt at 1.40% Li2O (Indicated) and 33.4 Mt at 1.33% Li2O (Inferred), ranking the Project as the largest lithium pegmatite resource in the Americas and among the top ten globally. Notably, the Project also hosts the world’s largest pollucite-hosted caesium pegmatite resource at the Rigel and Vega zones, further enhancing the Project’s critical mineral profile.

Strategic Positioning

The Shaakichiuwaanaan Project benefits from year-round road access and proximity to hydro-power infrastructure, contributing to development readiness.  

Conclusion 

The filing of the NI 43-101 Technical Report represents an important milestone for PMET Resources as it continues advancing the Shaakichiuwaanaan Project toward development. With a large-scale lithium resource, significant caesium potential, and favourable study outcomes, the Project strengthens PMET’s position in the North American critical minerals landscape. The company remains focused on advancing toward next-phase decisions while maintaining transparency through continued technical disclosure.