Highlights 

  • 12-year mine plan with after-tax NPV5% of USD 824 mn at consensus gold prices 
  • Average annual gold production of 141,000 oz forecast from 2026–2028 
  • Transaction IRR for CC&V exceeds 100% based on projected after-tax cash flows 

SSR Mining Inc. (TSX:SSRM) has released its 2025 Technical Report Summary for the Cripple Creek & Victor Gold Mine located in Colorado, USA. The report details a 12-year mine life and an after-tax net present value (NPV5%) of USD 824 mn, calculated using consensus gold prices averaging USD 3,240 per ounce across the mine’s life. 

At an elevated gold price assumption of USD 4,000 per ounce, the after-tax NPV5% rises to approximately USD 1.5 bn. Total proven and probable mineral reserves are estimated at 2.8 mn ounces of gold, supported by 4.8 mn ounces of measured and indicated mineral resources and 2.0 mn ounces of inferred resources, indicating room for potential resource conversion and future expansion. 

Production Outlook and Financial Metrics 

SSR Mining anticipates an average annual gold output of 141,000 ounces between 2026 and 2028. During this period, the company expects an average annual after-tax operating cash flow of USD 196 mn and a free cash flow of USD 128 mn. 

For the 2026–2030 span, total gold production is projected at 657,000 ounces, generating USD 761 mn in operating cash flow and USD 478 mn in free cash flow. The all-in sustaining cost is estimated at USD 2,051 per ounce from 2026–2028 and USD 2,135 per ounce from 2026–2030. 

The mine plan outlines total material mined at 373 mn tonnes, including 226 mn tonnes of ore, with an average grade of 0.39 grams per tonne and an average gold recovery rate of 51.6%. 

Management Statement 

Rod Antal, Executive Chairman of SSR Mining, commented, “The transformational acquisition of CC&V established SSR Mining as the third largest gold producer in the United States, with two core operations each with mine lives in excess of 10 years. Following a very successful integration process, CC&V has already paid back the initial USD 100 million upfront acquisition price in mine-site after-tax free cash flow. Including the total potential transaction outlay of USD 275 million, the results from this initial Technical Report Summary demonstrate a transaction IRR in excess of 100%, a truly exceptional outcome with meaningful growth potential for the operation still ahead.” 

Additional Information and Assumptions 

SSR Mining completed the acquisition of CC&V from Newmont in February 2025 through an upfront cash payment of USD 100 mn and up to USD 175 mn in additional milestone-linked payments tied to permitting and project milestones. Since the acquisition’s completion, CC&V has generated about USD 115 mn in mine-site after-tax free cash flow. 

Reclamation and closure costs associated with the mine are estimated at USD 517 mn under the 2025 TRS.