Key Highlights
- A published quote showed the stock up 1.33% at USD 1.90, along with a one-year EPS change of 61.69%, but the snapshot date and EPS basis are missing, so both remain unverified.
- Net income for the second quarter 2026 was USD 1.7 million; basic EPS registered USD 0.01 while diluted EPS turned negative at USD 0.02, per the August 13, 2026 release.
- Cash and restricted cash stood near USD 1.3 billion at June 30, 2026, with USD 530.3 million held inside the Thacker Pass joint venture.
- Department of Energy Loan advances have reached USD 1.209 billion in total, following a third advance of USD 342 million on June 3, 2026.
Why a 61.69% EPS Change Starts From a Tiny Base
Lithium Americas (NYSE:LAC) has not yet earned Revenue from its project, so its per-share figures are small and volatile. A ratio change from a near-zero or negative denominator can look enormous without reflecting any operating improvement. Q2 Net Income reached USD 1.7 million, although diluted EPS landed at negative USD 0.02, and six-month diluted EPS stood at negative USD 0.07. The 61.69% figure matched neither GAAP nor adjusted results, so it appears only as published market data with no verified basis. Thacker Pass in Nevada is still being built and has not produced lithium yet, which means reported Earnings contain no lithium sales. Any EPS growth rate is therefore a weak signal of project value, and the stated basis matters.
Thacker Pass Construction Pace and Funding Stack
Management says more than 1,600 workers are on site, detailed engineering is above 95% complete, and procurement has passed 80%. Roughly USD 1.8 billion of construction and project spending sits on the Balance Sheet as capitalized cost, and USD 1.6 billion of it counts toward the USD 2.93 billion capital estimate. The schedule calls for energization in the final quarter of 2026, with mechanical completion expected late in 2027. A definitive capital estimate was expected by the close of the third quarter of 2026; whether that happened is unverified. Guidance for 2026 capital spending runs USD 1.3 billion to USD 1.6 billion, and more than 2,000 workers are expected by year-end as more than 85% of structural steel arrives or is installed.
Dilution, Convertible Debt and a Quote That Does Not Reconcile
Share sales under the at-the-market program totaled 13.0 million by June 30, 2026, averaging USD 5.36 and netting USD 68.5 million. A USD 150 million first Tranche of convertible debentures closed on August 5, 2026, and up to USD 175 million is available in total. Both tools dilute holders. The USD 1.90 screen price is well beneath the USD 5.36 average sale price, which argues for caution with the quote. No market Capitalization is given. Tariffs could cost an estimated USD 80 million to USD 100 million, largely during 2026, and lithium prices, which the filing does not forecast, will determine project Economics once production starts.
Where Things Stand
Not on the evidence available. The 61.69% EPS change is only a published screen number: it sits on a tiny base, its basis is unknown, and reported diluted EPS for the quarter was negative. Lithium Americas (NYSE:LAC) reads better as a construction-stage project with heavy financing needs, where a 1.33% move carries little information. Energization at Thacker Pass, the definitive capital estimate and further dilution will count for more than one ratio. Gains at this stage can fade fast, and this analysis offers no forecast.