A revised mine plan for the Cadillac Project

How Cartier Resources Inc. (TSXV:ECR) is trying to turn a large gold resource near Val-d'Or into a development case is best seen through its September 2026 preliminary economic assessment (PEA) for the Cadillac Project. As of 18 November 2026, the explorer remains listed on the TSX Venture Exchange, and the updated study outlines a fully underground operation producing about 100,000 ounces of gold a year over 16.2 years, with a lower initial build cost than earlier thinking and Economics that are highly sensitive to the gold price. Agnico Eagle Mines is reported to hold about 27% of the company, which gives Cartier a strategic Shareholder in a district where Agnico is a dominant operator.

The PEA is a conceptual study, not a feasibility study, and the resources underpinning it include a large inferred component.

Company profile, listings and index status

Cartier, founded in 2006 and based in Val-d'Or, Quebec, is a gold exploration company focused on the Abitibi region. Besides its primary TSX Venture listing under ECR, the shares began trading on the OTCQB Venture Market in the United States under the symbol ECRFF on 30 April 2026, and they are also quoted in Frankfurt under 6CA. The OTCQB listing was intended to raise US visibility and liquidity.

In 2025 the company restructured its management team and narrowed its focus. It optioned its Wilson, Fenton and Benoist properties to Exploits Discovery Corp. under a four-year agreement requiring C$1.75 million in cash, 9.25 million Exploits shares and at least C$12.25 million of exploration spending for a full earn-in.

Resource base and the 100,000-metre programme

The Cadillac Project covers about 14,000 hectares along a 15-kilometre stretch of the Cadillac Fault, combining the historic Chimo Mine and East Cadillac properties. An updated NI 43-101 mineral resource estimate, announced in December 2025 with an effective date of 27 January 2026, reported measured and indicated resources of about 9.95 million tonnes at 2.40 g/t gold, or 767,800 ounces, and inferred resources of about 35.2 million tonnes at 2.14 g/t, or 2,416,900 ounces. The company described the inferred total as up 48% on the prior estimate. None of these resources are reserves.

Drilling is being carried out under a 100,000-metre diamond drilling programme launched in 2025, which the company described in January 2026 as on schedule and on budget. A July 2026 interview with management, put completion at roughly 35% and highlighted three areas outside the main deposit: the Contact Zone about five kilometres north-east of Chimo, the Portal area west of the Chimo shaft with existing ramp infrastructure, and the Hope area to the south. In March 2026 Cartier reported a new porphyritic intrusion-related gold system in Pontiac sediments at the Hope target. These discoveries sit outside the current economic model.

What the September 2026 PEA shows

The PEA assumes underground Mining of 23.1 million tonnes grading 2.28 g/t gold, recovering about 1.61 million ounces at 95% recovery. Ore would initially be toll milled at 3,000 tonnes a day, with an on-site plant ramping to 4,300 tonnes a day from year five. Reported initial Capital is about $198 million, with growth capital of about C$277 million and sustaining capital of roughly C$1.1 billion, for life-of-mine capital of about C$1.65 billion including closure.

At a base-case gold price of US$3,600 an ounce, the after-tax net present value at a 5% discount rate is about C$1.0 billion, with an after-tax internal rate of return of 26.6%. All-in sustaining costs are estimated at about $2,137 an ounce. The sensitivity table shows the dependence on metal prices: at US$3,000 the after-tax value falls to about C$497 million with a 16% return, while at US$4,300 it rises to roughly C$1.57 billion with a 37% return.

Compared with the 2023 Chimo PEA, which relied on sensor-based ore sorting to lift mill feed grades, the new plan mines more tonnage at a lower grade. The staged approach, using toll milling before building a plant, is what lowers the up-front cost, though it relies on access to third-party milling capacity.

Funding position and dividends

As an explorer, Cartier has no Revenue and funds itself through equity. In mid-2025 it reported about C$12 million in cash, which management said fully funded the drilling programme. By July 2026, management cited a treasury of more than C$5 million, enough for near-term work but implying that further financing is likely before the programme and follow-up studies are completed. Earlier raises have combined flow-through and hard-dollar units, which carry dilution for existing holders.

Cartier does not pay a dividend, and none would be expected at this stage.

Industry backdrop and key risks

Gold prices well above historical levels have improved the economics of many Abitibi projects and have encouraged consolidation in Quebec's gold belt, with larger producers taking stakes in or acquiring juniors. Proximity to mills near Val-d'Or helps a toll-milling start-up.

The risks are substantial. A large share of the resource is inferred and may not convert to higher categories. PEA outcomes depend on gold prices, costs and toll-milling arrangements that are not yet secured. The project still requires metallurgical, environmental and permitting work, and the company will need significant capital to advance it. Equity financing could dilute shareholders, and Agnico Eagle's large holding means one shareholder's decisions could heavily influence Cartier's strategic options.

Milestones to monitor

The company has guided to metallurgical and environmental baseline studies, originally slated for the second and third quarters of 2026, and to continuing drill results from the 100,000-metre programme, which management has said runs to around Easter 2027. Further resource updates incorporating the Contact, Portal and Hope areas, any new financing, and any next-stage study would be the main disclosures to watch.