Rio2 Limited (TSX:RIO) · S&P/TSX SmallCap
Rio2 Limited (TSX:RIO) spent years as a gold developer waiting to build its Fenix Gold project in Chile. In 2026 that project finally came to life: Fenix poured its first gold in January and has been ramping up towards commercial production ever since, which is why the Vancouver-based company is attracting attention among smaller Canadian Mining names.
The headline's "developer" label is now only partly accurate. Rio2 is still in the ramp-up phase at Fenix, with commercial production targeted for the fourth quarter of 2026, but it has also become a copper producer after completing the Acquisition of the Condestable mine in Peru on 30 January 2026. The company now describes itself as pursuing a dual gold and copper strategy aimed at becoming a diversified Latin American miner.
Rio2 is a member of the S&P/TSX SmallCap Index, the benchmark tracking smaller companies on the Toronto Stock Exchange. The shares closed at C$3.90 on 22 September 2026, up 8.3% on the day, within a 52-week range of C$1.655 to C$4.09, giving a Market Value of roughly C$2.1 billion. The precise reason for that single-day move is not clearly identifiable, although the company published a company-wide exploration update the same day.
Fenix: from first pour to ramp-up
Fenix is a 100%-owned gold mine in Chile. The company announced that its first gold pour took place on 23 January 2026, yielding about 897 ounces, which together with 358 ounces recovered during December commissioning brought early output to about 1,255 ounces. Chief executive Andrew Cox said the team had achieved first gold after a construction period of about 14 months, and executive chairman Alex Black described it as the culmination of an eight-year journey delivered on budget.
At that time, Rio2 set a 2026 production target of 60,000 to 70,000 ounces, with ore mining planned to reach 20,000 tonnes per day by the end of 2026. The company also points to about 100,000 ounces in 2027.
The ramp-up has not been smooth. In the Q2 2026 results, Rio2 said one of the strongest El Niño events on record brought heavy snow and extremely low temperatures to the high-altitude Fenix site late in the quarter, continuing into July and August. It estimated that about 265,000 tonnes of ore mining and roughly 5,000 ounces of gold production had been deferred, and it withdrew full-year Fenix guidance because of the unpredictability of the weather and the ongoing ramp-up. Even so, the ore mining rate rose from 13,600 tonnes per day in April to 16,100 tonnes per day in June, and the company completed a switch to larger 42-tonne trucks.
Adding copper through Condestable
Rio2 acquired a 99.1% interest in the Condestable underground copper, gold and silver mine from Southern Peaks Mining L.P. and Adolfo Vera. The consideration included a US$55 million secured Promissory Note and a US$10 million subordinated mezzanine note, both with six-year terms, along with shares and cash. To help fund the transaction, Rio2 closed an upsized bought deal of 86.1 million subscription receipts at C$2.22 each for gross proceeds of about C$191 million on 15 December 2025, followed by a C$14 million brokered private placement.
The company has said Condestable targets around 27,000 tonnes of copper equivalent a year. On 21 August 2026, Peruvian regulators approved a modified environmental impact assessment that allows throughput to increase from 8,400 to 10,000 tonnes per day, approves a new dry-stack tailings Facility and extends environmentally approved operations by about a decade. Rio2 said it plans to complete engineering studies and make a final Investment decision on the expansion in the second half of 2026.
Q2 2026 results in figures
For Q2 2026 (three months to 30 June 2026), reported in US dollars, Rio2 posted consolidated Revenue of US$105.3 million, Net Income of US$46.8 million and adjusted net income of US$17.1 million. Adjusted EBITDA was US$46.5 million, and cash stood at US$49.7 million at quarter-end.
Fenix produced 9,088 ounces of gold and sold 6,814 ounces at an average realised price of US$4,163 per ounce. Costs remain high during ramp-up, with all-in sustaining costs of US$2,873 per ounce sold. Condestable produced about 9.3 million pounds of copper, plus 4,451 ounces of gold and 74,374 ounces of silver, at all-in sustaining costs of US$3.10 per pound against a realised copper price of US$5.94 per pound. Guidance for Condestable is 21,500 to 23,500 tonnes of payable copper equivalent for February to December 2026.
Exploration and index recognition
On 22 September 2026, Rio2 said it had begun a first-phase surface drilling programme of 16,750 metres at Condestable, with a second phase of 17,120 metres pending permits. At Fenix, drilling has been suspended until January 2027 because of weather and safety considerations, with an updated resource estimate expected in December 2027. The company also plans scout drilling at its Kalzas tungsten project in Canada in 2027. Separately, Rio2 announced on 14 September 2026 that it had been added to the MVIS Global Junior Gold Miners Index.
Risks to weigh
Weather has already shown it can disrupt Fenix, and ramp-up periods often bring cost overruns and technical setbacks. Gold and copper prices are volatile, and today's elevated prices are a major support for margins. Rio2 now carries acquisition-related promissory notes and operates in two jurisdictions, Chile and Peru, each with its own regulatory, political and community considerations. Shareholders have also seen dilution from recent equity financings, and a final decision on the Condestable expansion could require further capital.
What investors may watch next
Key milestones include whether Fenix declares commercial production in the fourth quarter of 2026 as targeted, how quickly mining rates reach 20,000 tonnes per day, the Condestable expansion investment decision and the progress of the new drilling campaign. Third-quarter results should also show how much the El Niño disruption affected output.
Rio2 has moved from a single-asset developer to a two-mine producer in less than a year. Whether that transition translates into steady Cash Flow is likely to depend on the pace of the Fenix ramp-up, conditions in the Andes and the direction of metal prices.