Troilus Mining Corp. (TSX:TLG), which changed its name from Troilus Gold Corp. in December 2025, is trying to bring a former gold-copper mine in northern Quebec back into production on a much larger scale. The Montreal-based developer has spent 2026 moving from studies to execution planning, and on 9 September 2026 it filed an updated technical report that, at the study's price assumptions, points to a 50,000-tonne-per-day open-pit operation with an after-tax net present value of about US$3.2 billion.

The market has repriced the company over the past year. The shares stood at C$2.35 on 8 September 2026, against a 52-week range of C$0.95 to C$2.47, giving a Market Value of roughly C$1.24 billion on about 555 million shares. That rerating, alongside progress on financing, power and procurement, explains why Troilus is drawing attention within the S&P/TSX SmallCap Index, which tracks smaller Canadian-listed companies.

The headline's premise holds, with a caveat: Troilus is eyeing production, but a formal construction decision has not yet been made and the project still depends on permits and financing.

From historic mine to large-scale development project

The Troilus project covers about 435 square kilometres in the Frotêt-Evans Greenstone Belt, north-east of Val-d'Or. The site hosted a gold and copper mine in the past, and the company's strategy is to restart it as a far larger, long-life operation producing a copper-gold concentrate. Troilus completed basic engineering on 24 March 2026, and detailed engineering was fully mobilised by June, with more than 40 bid packages issued or under evaluation at that time.

What the September 2026 technical report shows

The updated NI 43-101 report uses base-case prices of US$3,600 per ounce of gold, US$5.00 per pound of copper and US$50 per ounce of silver. On that basis, the company reported an after-tax NPV at a 5% discount rate of US$3.206 billion, an after-tax internal rate of return of 22% and a payback period of 3.6 years. The pre-tax figures were an NPV of US$5.266 billion and an IRR of 27%.

Initial Capital is estimated at US$1.428 billion, including capitalised operating costs but excluding sunk costs through the first quarter of 2027. Sustaining capital is put at US$198 million over the life of the mine and closure costs at US$52.4 million. All-in sustaining costs are estimated at US$1,340 per ounce of gold after copper and silver credits.

The plan envisages a 26-year life, comprising one pre-production year, 21 years of mining and four years of stockpile processing. Over the full life, the report projects total payable production of 5.63 million ounces of gold, 472 million pounds of copper and 10.88 million ounces of silver. Average annual output over years one to 21 is projected at 251,000 ounces of gold, 20.1 million pounds of copper and 466,000 ounces of silver. Proven and Probable Reserves stand at 478 million tonnes grading 0.44 grams per tonne gold, 0.05% copper and 0.92 grams per tonne silver, containing about 6.7 million ounces of gold, which the company said was a 26% increase on its 2024 feasibility study. The capital estimate rests on about 95,000 engineering hours and roughly 90% market-validated pricing, meeting AACE Class 3 accuracy standards.

Investors should remember that these are study projections rather than results, and that the Economics are sensitive to the metal prices assumed.

Building the financing and Supply chain

Funding a project of this size is the central challenge. Troilus is advancing a US$1.2 billion senior secured project financing mandate, with Société Générale, KfW IPEX-Bank and Export Development Canada as mandated lead arrangers, alongside Canadian and European export Credit agencies.

On 25 August 2026, the company selected Metso for major process equipment, targeting definitive arrangements in September. Two days later, it said Finland's export credit agency Finnvera had issued a non-binding letter of interest for up to approximately US$132 million, covering 85% of an estimated US$155 million Metso package. The company noted the letter remains subject to Due Diligence and final approvals.

Infrastructure and permitting have also moved forward. On 2 June 2026, Troilus announced a full 70-megawatt power allocation from Hydro-Québec and the Quebec government, and on 27 July it said Quebec had selected the project for specialised permitting support under its Filon initiative for strategic mining projects. Federal and provincial permitting processes are advancing in parallel.

Drilling beyond the reserve

While engineering proceeds, Troilus has kept drilling. On 20 August 2026 it reported 8.84 grams per tonne gold-equivalent over 4.8 metres at the Z87 zone, about 300 metres beyond the existing resource, with mineralisation traced up to 400 metres past the current pit shell. An earlier release on 23 July reported 1.10 grams per tonne gold-equivalent over 103 metres from the Z87 optimisation programme. In June, the company also reported 1.15 grams per tonne gold-equivalent over 37 metres at the Connector Zone and said it was continuing to expand a high-grade discovery at West Rim. The company said the Z87 results would feed into future model updates and assessments of scale and longer-term development options.

Risks on the road to production

The largest risk is financing. The US$1.2 billion mandate and the Finnvera letter are not binding commitments, and the remaining funding could involve Equity dilution, streams or other instruments whose terms are unknown. Capital cost overruns are common in large mine builds, and a Class 3 estimate still carries a range of uncertainty. Permits have not yet been granted, and schedules can slip because of consultation, environmental review or labour and equipment availability. The project's economics lean heavily on high gold prices; a significant fall would weaken the case. Low-grade, bulk-tonnage operations also leave little Margin for error on recoveries and costs.

What investors may watch next

According to the technical report, Troilus anticipates construction starting in 2027, first ore in September 2029 and commercial production in March 2030, all subject to approvals and financing. Near-term markers include definitive agreements with Metso, progress on the Debt package, permitting milestones, further Z87 drilling and a formal construction decision.

Troilus has moved closer to becoming a producer this year, but the hardest steps, locking in financing and securing permits, still lie ahead. How it handles them will likely shape the company's path over the coming 12 to 18 months.