Buffalo Potash (TSXV:BUFF) shares climbed on the TSX Venture Exchange on Thursday, October 1, as investors kept buying into the company's push toward first production in Saskatchewan. Last week it said it had finished drilling all the wells for its first small-scale potash module at the Disley project. The company had not issued a new release by Thursday's close, so the gain looks like a continuation of that story.

What happened

The stock closed at C$1.00, up about an eighth. Volume was roughly 398,000 shares, giving the company a Market Value near C$88 million.

The shares have been on a run. They climbed from around C$0.80 in mid-September to about C$1.01 on September 24, the day before the drilling news, then gave back some ground before Thursday's rebound.

On September 25, Buffalo Potash said it had completed the third and final Horizontal Well at its Disley Initial Production Module. That finished the full set of five wells the module needs. The next step is brine circulation, the commissioning stage that comes before any potash is produced.

Why it matters

Finishing the wells removes a key execution risk. Buffalo Potash uses a patented horizontal line-drive method, a form of selective solution mining. Instead of digging shafts, it pumps fluid through horizontal wells to dissolve potash underground and brings the brine to the surface for processing.

The initial module is designed to produce 125,000 tonnes a year. The company is targeting first production in the first quarter of 2027, based on assumptions in its preliminary economic assessment. That would be fast by Mining standards, where new projects often take the better part of a decade to reach output.

Permitting also moved forward last month. On September 17, the company said Saskatchewan's Ministry of Environment had determined the module was not a "development" under provincial rules, so no environmental impact assessment is required. That clears away a step that can add many months to a project timeline.

A junior moving from drilling to near-term production often draws a new group of investors. That shift appears to be playing out here.

The bigger picture

The Disley project covers about 10,610 hectares, roughly 50 kilometres northwest of Regina. It sits next to K+S's Bethune mine and Mosaic's Belle Plaine mine, two established solution potash operations.

In July, Buffalo Potash laid out a plan to grow beyond the initial module. Full build-out could reach up to 1,125,000 tonnes a year across three facilities. Its preliminary economic assessment showed an after-tax net present value of about US$1.1 billion. The company has funded its work through an oversubscribed private placement, closing a first Tranche of about C$14 million earlier this year.

Potash is a crop nutrient, and Saskatchewan holds some of the world's largest reserves. Demand tends to track farm incomes and global food needs.

Thursday's gain bucked a weak market. Materials stocks were among the biggest drags on the S&P/TSX Composite, which slipped to a one-month low. The S&P/TSX Venture index finished roughly flat.

What to watch next

The next milestone is brine circulation, followed by early results on how well the wells perform. After that, investors will want to see the surface processing plant take shape on schedule.

The company itself has warned there is no guarantee the module will be completed as expected or at all. Early-stage projects often face delays, cost overruns or technical hiccups, and preliminary economic studies carry wide margins of error.

For now, the market is rewarding Buffalo Potash for hitting its drilling targets on time.