Angkor Resources Corp. (TSXV: ANK | OTCQB: ANKOF) has announced that its Cambodian energy subsidiary, EnerCam Resources Co., Ltd., has completed hosting the final potential drilling contractor at target drill sites on Block VIII. The milestone positions EnerCam to receive final competitive bids for its 4+1 multi-well exploratory drilling programme once Cambodia's Ministry of Mines and Energy approves the drilling tender. The programme would mark the first privately financed onshore oil and gas wells drilled in Cambodia, a country that currently imports 100% of its hydrocarbon-based energy products.
Key Points
- Angkor Resources Corp. (TSXV: ANK | OTCQB: ANKOF) and its subsidiary EnerCam Resources Co., Ltd.
- EnerCam has completed all contractor site visits, clearing the path for final drilling quotations on its Block VIII 4+1 well programme
- Bidders have six weeks to submit bids; mobilisation of a drilling rig is estimated at approximately three months once a contractor is engaged
- Investors may be watching for Ministry of Mines and Energy tender approval and the selection of a drilling contractor
EnerCam's Block VIII Contractor Visit Process Now Complete
EnerCam hosted the final potential drilling contractor across its five target drill sites on Block VIII, a licence covering approximately 4,095 km² in southwest Cambodia under a 30-year Production Sharing Contract with the Royal Government of Cambodia. The company stated that having contractors physically assess each site ensures they are bidding with full knowledge of conditions, which the release suggests is intended to generate competitive pricing across the entire programme. Ministry of Mines and Energy approval of the tender is described as upcoming, after which EnerCam will distribute the tender to pre-qualified drilling companies for formal pricing.
Structure of the 4+1 Exploratory Well Programme Across Four Sub-Basins
The drilling programme calls for at least one exploration well in each of four sub-basins — Bokor South, Bokor Central, Bokor North, and Kirirom — with a fifth well to be sited based on results from the initial four. EnerCam previously completed 350 line-kilometres of 2D seismic to define these targets and has received Environmental Impact Assessment approval from Cambodia's Ministry of Environment. The company's work is underpinned by its Production Sharing Contract and is focused on proving the existence of a domestic hydrocarbon supply in a nation that presently relies entirely on imported energy products.
Timeline to Drilling Dependent on Bid Review and Rig Mobilisation
According to the release, pre-qualified contractors have six weeks to finalise and submit their bids. Once a contractor is selected, mobilising the drilling rig, equipment, and supplies into Cambodia and to the first site is estimated to take approximately three months. EnerCam President Mike Weeks was quoted in the announcement stating the site visit process gives EnerCam competitive pricing on each well and that the company can then select a contractor and advance drilling of what the release describes as Cambodia's first onshore oil and gas wells. The company did not disclose estimated drilling costs in the announcement.