First Quantum Minerals Ltd. (TSX: FM) reported net earnings of $136 million ($0.16 per share) for the second quarter of 2026, driven by strong copper sales volumes and higher realized prices. The company achieved a significant operational milestone at its Cobre Panamá mine with the successful commissioning of one of three processing circuits and first concentrate production from stockpiled ore, while an independent environmental audit confirmed 87.7% overall compliance with commitments. Despite an adjusted loss of $106 million reflecting hedge program losses and pre-production costs, the company expects improved cash flow generation in the second half of 2026 as production ramps up across its portfolio.
Key Points
- First Quantum Minerals Ltd. (TSX: FM) reported Q2 2026 net earnings of $136 million ($0.16 per share) and EBITDA of $400 million
- Cobre Panamá achieved first copper concentrate production of 3,216 tonnes in May 2026 following successful commissioning of one processing circuit for stockpiled ore
- Total copper production reached 100,487 tonnes in Q2 2026, a 4% increase from Q1 2026, with realized copper prices of $5.34 per pound versus $5.16 in the prior quarter
- An independent environmental audit confirmed 361 of 370 commitments fulfilled (87.7% compliance), and the Government of Panama formed a ministerial committee to review findings
Q2 2026 Financial Performance Reflects Higher Copper Prices and Production Gains
First Quantum reported consolidated Q2 2026 results demonstrating improved profitability compared to the first quarter. Gross profit of $297 million was $19 million higher than Q1 2026, while EBITDA of $400 million increased by $74 million, primarily attributable to higher copper sales volumes and realized copper prices of $5.34 per pound, up from $5.16 in the prior quarter. Net earnings attributable to shareholders reached $136 million, or $0.16 per share, contrasting sharply with a loss of $196 million in Q1 2026.
The company's reported EBITDA of $400 million included several offsetting adjustments: the company realized losses of $164 million under its sales hedge program during the quarter and recognized a negative EBITDA contribution of $51 million from Cobre Panamá associated with preservation and site maintenance costs prior to commercial production commencement. Notably, all sales hedges were completed by June 30, 2026, and the company now has no commodity contracts designated as hedged instruments, positioning it for full exposure to copper price movements going forward.
Cobre Panamá Stockpile Processing Commences Ahead of Schedule
A pivotal operational achievement in Q2 2026 was the successful commissioning of the first of three milling circuits at Cobre Panamá, enabling earlier-than-expected concentrate production from stockpiled ore. The Government of Panama authorized the removal, processing, and export of stockpiled ore on April 7, 2026, through Resolution No. 27, designed to mitigate environmental and operational risks from prolonged on-site storage. The first circuit was successfully commissioned in May 2026, immediately followed by the commencement of stockpile processing and production of the first copper concentrate of 3,216 tonnes during the second quarter.
The processing program is proceeding from a substantial reserve base: approximately 2.1 million tonnes of ore was processed during Q2 2026 at an average head grade of 0.23% copper with recoveries of 67%. The total estimated stockpile comprises approximately 38 million tonnes of mineralized ore at varying grades, containing approximately 70,000 tonnes of recoverable copper, sufficient to support twelve months of processing at current operational rates. First Quantum provided unchanged guidance for copper production from stockpiled ore processing at Cobre Panamá of 30,000 to 40,000 tonnes in 2026. The company has shifted its operational focus towards stabilizing the first processing train while progressively addressing refurbishment, maintenance backlogs, and commissioning of additional plant equipment. The power station has been fully recommissioned, and excess power is being sold to support Panama's national grid, partially offsetting incremental power plant costs.
Environmental Compliance Audit Delivers Positive Assessment at Cobre Panamá
An independent environmental compliance audit conducted by SGS at Cobre Panamá was completed in Q2 2026 and released by the Ministry of Environment on June 19, 2026, delivering a favourable assessment of the mine's environmental performance. The audit confirmed that 361 of 370 environmental commitments were fulfilled, representing an overall compliance rating of 87.7%. The independent assessment identified seven partial compliances, primarily related to opportunities for further enhancement of biodiversity management and ecological restoration measures, and three non-compliances associated with reforestation programs that have remained suspended since 2023 following the suspension of operations.
The audit report noted that non-compliances and partial compliances relate principally to long-term reforestation, biodiversity, and restoration programs that are correctable in nature and are not associated with acute environmental incidents. No areas were identified as fundamentally absent or unimplemented. In response to the audit findings, the Government of Panama established a high-level ministerial commission during Q2 2026, comprising the Ministers of Commerce and Industries, Economy and Finance, and Environment, to evaluate matters relating to the future of Cobre Panamá, including consideration of the independent audit findings and associated economic, environmental, and legal implications. First Quantum stated in the announcement that it remains ready to engage constructively with the Government of Panama to achieve a fair and durable resolution for the mine.
Copper Production Growth Across Operating Portfolio
Total consolidated copper production for Q2 2026 reached 100,487 tonnes, representing a 4% increase from 96,469 tonnes in Q1 2026. This growth was primarily driven by higher production at Sentinel, which produced 50,335 tonnes in Q2 2026 (up 5,083 tonnes from the prior quarter), and the commencement of 3,216 tonnes of copper production from Cobre Panamá stockpile processing. The gains were partially offset by the disposition of Çayeli on April 30, 2026. Kansanshi reported copper production of 43,997 tonnes, down 1,348 tonnes from the prior quarter due to planned maintenance, though the S3 circuit sustained throughput above design capacity. Copper sales volumes totaled 93,300 tonnes in Q2 2026, approximately 7,187 tonnes lower than production due to timing differences between sales and production.
Production costs remained elevated despite higher volumes. Excluding Cobre Panamá, the company's C1 copper cash cost improved by $0.03 per pound quarter-over-quarter to $2.48 per pound, benefitting from improved production volumes at Sentinel and higher capitalized stripping costs, which offset the impact of higher fuel prices and lower gold by-product credits resulting from a weakening gold price. Including Cobre Panamá, copper C1 cash cost was $2.54 per pound, $0.03 higher than Q1 2026, reflecting higher-cost production from the restarted operation. Copper all-in sustaining cost (AISC) excluding Cobre Panamá was $4.14 per pound compared to $3.96 per pound in Q1 2026, while total AISC including Cobre Panamá was $4.27 per pound versus $4.05 per pound in the prior quarter.
Kansanshi S3 Circuit Delivers Highest Monthly Processing Rates
At Kansanshi, the S3 circuit expansion continued to demonstrate strong operational performance in Q2 2026, achieving the highest monthly processing rate in May 2026 since commissioning in August 2025. The S3 circuit operated at throughput levels above design capacity during the quarter, driven by higher operating time, strong equipment utilization, and elevated milling rates. The circuit continues to process a high proportion of feed from surface stockpiles, which are lower in grade and more difficult to process than fresh mined ore, yet the operation has sustained above-design-capacity performance, supporting the Company's strategy of processing lower-grade long-term stockpiles.
Copper production at Kansanshi for Q2 2026 was 43,997 tonnes, down 1,348 tonnes from the prior quarter, primarily due to planned maintenance of the S3 and mixed circuits. However, copper C1 cash cost increased to $2.16 per pound from $1.69 per pound in Q1 2026, reflecting higher fuel and consumable costs and lower gold by-product credits due to the weakening gold price. The company maintained its 2026 copper production guidance for Kansanshi at 175,000 to 205,000 tonnes and gold production guidance at 110,000 to 120,000 ounces. Management expects higher S3 throughput in the second half of 2026 sourced from low-grade, lower-recovery stockpiles, with fresh ore from the South East Dome—which is harder and higher grade—to be gradually introduced into the S3 circuit during the second half of the year.
Sentinel Delivers Strong Cost Reductions Amid Planned Maintenance
Sentinel operations reported copper production of 50,335 tonnes in Q2 2026, an increase of 5,083 tonnes from the prior quarter, as higher grades and recoveries offset lower throughput caused by the annual planned total plant shutdown at Trident, which was completed in June. Copper C1 cash cost of $2.84 per pound decreased by $0.60 per pound from the prior quarter, primarily as a result of higher production volumes. Despite higher diesel prices impacting costs in Q2 2026, this was offset by lower employee costs. First Quantum maintained unchanged 2026 production guidance for Sentinel of 190,000 to 220,000 tonnes of copper.
The company is addressing ongoing challenges with ball mill flange bolt fatigue in collaboration with the Original Equipment Manufacturer and engineering consultants, with planning underway for a major upgrade in 2027 involving replacement of a section of the discharge end with a new OEM design to provide a permanent engineered solution. The focus at Sentinel remains on increasing mill throughput and improving recoveries through initiatives to optimize feed grade, blast fragmentation, stockpile management, milling performance, and flotation efficiency. First Quantum expects grades to improve in the second half of 2026 as mining progresses within Stage 2, with Stage 3 ore increasingly supplementing feed from Stage 1 and Stage 2.
Enterprise Nickel Operations and Guelb Moghrein Continue Production
Enterprise operations produced 11,246 tonnes of contained nickel in Q2 2026, a 9% decrease from the prior quarter mainly due to the annual planned total plant shutdown at Trident, which was completed during June. Nickel C1 cash cost of $2.75 per pound increased by $0.23 per pound from the prior quarter due to lower production volumes. First Quantum maintained unchanged 2026 production guidance for Enterprise of 30,000 to 40,000 tonnes of contained nickel at a nickel unit cost guidance of $3.25 to $4.25 per pound. Operational priorities remain focused on improving ore quality and grade control through ongoing reverse circulation drilling, with mining practices being refined—including reduced ore bench heights—to minimize dilution and enhance recovery.
Guelb Moghrein contributed 2,031 tonnes of copper and 6,310 ounces of gold production in Q2 2026. First Quantum maintained unchanged 2026 production guidance for Guelb Moghrein of 7,000 tonnes of copper and 30,000 to 40,000 ounces of gold. The operation continued processing sulphide copper ores plus gold-containing tailings through CIL during 2026, with intermittent treatment of stockpiled oxide gold ore to support the most favourable transition to full oxide ore gold production.
Cash Flow and Balance Sheet Developments
Cash flow from operating activities for Q2 2026 totalled $130 million ($0.16 per share), attributable to net earnings of $78 million along with favourable movements in working capital. However, net debt increased by $123 million during the quarter to $5,407 million at June 30, 2026, primarily reflecting capital expenditures of $322 million and taxes paid of $199 million, partially offset by EBITDA contributions of $400 million. For Cobre Panamá specifically, the company estimated total required capital at approximately $250 million, primarily comprised of working capital to replenish inventories. Cash outflows are expected to include plant and equipment recommissioning (estimated at $90 million to $100 million for commissioning), warehouse inventory replenishment ($40 million to $50 million for inventory), and sustaining capital ($75 million to $100 million). As of Q2 2026, cumulative cash outflows in relation to these costs totalled approximately $60 million.
The immediate share price impact was not clear from available public information. First Quantum's financial position reflects the company's transition from a period of operational suspension to the commencement of production at Cobre Panamá, with the sequencing of capital deployment expected to support improved cash generation in the second half of 2026 as copper production expands across the portfolio.
Cost Pressures from Fuel Prices and Currency Movements
First Quantum highlighted ongoing cost pressures from elevated fuel prices and Zambian kwacha movements that are expected to impact operational results in the second half of 2026. The company noted a potential impact to C1 copper cash costs of approximately $0.25 per pound to reflect the year-to-date impact of higher fuel prices and Zambian kwacha rates, as well as potential further impact if current fuel prices and Zambian kwacha rates persist for the remainder of the year. After several weeks of improving diesel availability and gradually easing prices in early 2026, subsequent to the second quarter, renewed geopolitical developments—including oil refinery disruptions in the Middle East, Russia's suspension of diesel exports, and renewed uncertainty surrounding the Strait of Hormuz—have re-introduced volatility into global diesel markets and increased supply risk for import-dependent consumers in East Africa.
The company noted that its regular supply chain contained sufficient diesel for at least two months of operations as of the announcement date, with potential to extend coverage beyond this timeframe through close monitoring. First Quantum stated that it continues to evaluate alternative supply routes with the possibility to extend coverage if escalation continues. Costs in the third quarter are expected to continue to be impacted by higher fuel pricing, representing an ongoing headwind to production cost guidance and profitability expectations.
Operational Guidance Unchanged; Hedging Program Concluded
First Quantum confirmed that 2026 guidance remains unchanged across its operating portfolio, though the company continues to flag the previously disclosed potential impact to C1 copper cash costs. With the completion of all sales hedges by June 30, 2026, the company is now fully exposed to copper price movements, which management noted positions the company for improved free cash flow generation at current copper prices alongside stronger production anticipated in the second half of 2026. The company stated that improved production from the S3 circuit at Kansanshi, debottlenecking work at Sentinel, and the processing of stockpiled ore at Cobre Panamá are expected to support cash flow improvement in the remainder of the year.
The CEO commentary in the announcement noted encouragement regarding progress at Cobre Panamá, particularly the release of the final audit report and formation of the inter-institutional ministerial committee to review its findings. Management stated readiness to engage constructively with the Government of Panama to achieve a fair and durable resolution that serves the best interests of the country and its people as well as the company's stakeholders. This constructive engagement framework represents a significant development following the mine's operational suspension and subsequent authorization to process stockpiled ore.