Forge Resources Corp. (CSE: FRG) (OTCQB: FRGGF) (FSE: 5YZ) announced on October 22, 2026, that the underground junction at its fully permitted La Estrella coal project in Santander, Colombia, is complete and the crosscut has advanced 15 metres toward the first of eight known coal seams. The company estimates that approximately 25 additional metres of crosscut development will bring the heading to the first seam. Investors are watching the milestone closely, as the company describes reaching the first coal seam as a pivotal step on La Estrella's path toward extraction and cash flow.

Key Points

  • Forge Resources Corp. (CSE: FRG) is a Canadian-listed junior exploration company with an 80% interest in the La Estrella coal project in Colombia.
  • The underground junction connecting the ramp to the crosscut is fully complete, with 15 metres of crosscut advance recorded to date.
  • The first coal seam is estimated to be approximately 25 metres of additional crosscut advance away.
  • Investors may be watching the planned ventilation, power, and mucking infrastructure upgrades as indicators of operational readiness ahead of first seam contact.

Junction Completion and Crosscut Profile at La Estrella

The underground junction linking the ramp to the crosscut at La Estrella has been fully completed, allowing the heading to advance directly toward the coal seams. Of the 15 metres completed to date, 10 metres were excavated on a 12.4 m² steel arch profile and 5 metres on a streamlined 9.0 m² profile. The release states that the smaller profile is improving excavation, loading, and muck-handling efficiency. The ramp base has reached 149.5 metres of advance, with the crosscut junction visible at that point, according to photographic documentation included in the announcement.

Infrastructure Upgrades Planned to Support Continued Crosscut Advance

To sustain development momentum as the crosscut lengthens toward the coal seams, Forge Resources has outlined a package of site infrastructure improvements. The company is planning installation of an additional 30 HP explosion-proof axial fan approximately 120 metres along the underground ramp to reinforce air pressure and fresh air flow to the working face. On the power side, on-site electrical generation capacity is planned for an upgrade from 60 kW to 175 kW to support the expanded ventilation system and new equipment. Mucking upgrades are also included in the planned package, the release states.

La Estrella's Eight Coal Seams and the Path Toward Cash Flow

La Estrella is described in the announcement as hosting eight known seams of metallurgical and thermal coal. The company holds its interest in the project through an 80% stake in Aion Mining Corp., the project development entity. CEO PJ Murphy stated that the team is on a direct line to the coal seams and that reaching the first seam will mark a pivotal milestone for Forge Resources. The technical information in the release was reviewed and approved by Emilio Gene, P.Eng., Project Director and Mining Engineer, as a Qualified Person under National Instrument 43-101.