GoGold Resources Inc. (TSX: GGD) has released a construction update on its Los Ricos South silver-gold project in Jalisco, Mexico, confirming the project remains on schedule. Site clearing and earthworks are approximately 48% complete, with 180 contractor personnel currently on site. The company reiterates its target of a first silver pour in the second quarter of 2028, a milestone investors have been closely monitoring since construction was approved.
Key Points
- GoGold Resources Inc. (TSX: GGD / OTCQX: GLGDF) issued a Los Ricos South construction progress update on November 23, 2026.
- Site earthworks are roughly 48% complete; all long-lead equipment orders have been placed and remain on schedule.
- The company has spent US$21 million to date, with US$52 million committed; using internal estimates at US$45/oz silver, GoGold expects cash reserves to remain above US$100 million throughout the build.
- Investors may be watching whether key January 2027 construction milestones — including paste plant construction, concrete foundation pouring, and portal development — are achieved on schedule.
Los Ricos South Earthworks and Engineering Reach Key Milestones
GoGold reports that site clearing and earthworks at the process plant are approximately 48% complete, with plant design by M3 and DENM Engineering standing at 95% complete. All long-lead equipment orders — including the SAG mill, tailings filter, crusher, Merrill-Crowe plant, and paste plant pumps — have been placed. The SAG mill is scheduled for delivery to site in May 2027, while plant commissioning is targeted to begin in January 2028. The release states that construction and procurement remain on or ahead of plan.
Underground Mining Contractor Mobilises as Paste Plant Design Advances
Underground mining contractor Cominvi was planned to mobilise to site in the fourth quarter of 2026, with portal designs completed by WSP and associated earthworks already under way. Paste plant design is being carried out by RMS of Sudbury, Canada, with current progress expected to allow construction to begin in January 2027. Hill-slope stabilisation and mining at the Main and Abra zones are targeted for March 2027. The release states that portal development and ramp blasting are also scheduled to commence in January 2027.
GoGold Balance Sheet Cited as Project Completion Cushion
The company disclosed that US$21 million has been spent on Los Ricos South to date, with US$52 million committed. Management stated that cash flows from the operating Parral Tailings mine in Chihuahua, combined with the company's existing balance sheet, are expected to fund project completion without requiring additional equity or debt offerings. Using internal estimates based on US$45 per ounce silver, GoGold projects cash reserves will remain at a minimum of US$100 million throughout the construction period, the release states.