Honey Badger Silver Inc. (TSXV: TUF) has announced results of a comprehensive process plant condition assessment for its 100%-owned PC Silver Mine in the Northwest Territories, Canada, conducted by Tusk Automation Inc. The assessment concluded that the existing processing infrastructure can be refurbished and restarted in phases, with no conditions identified that would prevent its restart. The company's Board of Directors has approved Phase 1 of the plan, targeting crushing circuit recommissioning at an estimated cost of C$1.8 million. The phased approach envisions proof-of-concept testing in 2027 and lead and zinc concentrate production at 1,000 tonnes per day by mid-2028.
Key Points
- Honey Badger Silver Inc. (TSXV: TUF) (OTCQB: HBEIF) operates the fully permitted, high-grade PC Silver Mine in the Northwest Territories
- Tusk Automation confirmed the existing plant can be restarted with no conditions preventing recommissioning
- Phase 1 cost estimated at C$1.8 million; Phase 2 at C$12.6 million; Phase 3 at C$21.2 million — totalling C$35.6 million across all three phases, with an additional C$8.0 million in estimated fuel and air transportation costs
- Phase 2 and Phase 3 remain subject to further engineering, capital allocation, permitting, and financing
Tusk Automation Confirms PC Silver Plant Condition and Phased Recommissioning Path
Following a detailed on-site inspection, Tusk Automation found the PC Silver Mine's crushing circuit substantially complete and in good mechanical condition, while grinding and dewatering equipment was assessed as very good and suitable for refurbishment. The release states this outcome supports reuse of substantial existing processing equipment, conceptually reducing capital requirements and development timelines relative to building an entirely new facility. The PC Silver Mine hosts five kilometres of existing underground workings and a polymetallic mineral resource containing silver, zinc, lead, copper, and antimony.
Board Approves Phase 1 Crushing Circuit Restart at C$1.8 Million
Honey Badger Silver's Board of Directors has approved Phase 1 of Tusk's restart plan, which covers refurbishment and recommissioning of the crushing circuit from the ore receiving system through to the fine ore storage bin. Work includes refurbishment of crushers, conveyors, electrical equipment, and associated infrastructure. Tusk has identified the opportunity to complete Phase 1 activities during the 2026–2027 winter season, subject to procurement, mobilisation, and site readiness. The Phase 1 estimate is classified as a Class 2 estimate and includes a 15% contingency.
Three-Phase Capital Cost Structure and Full Production Target for 2028
Tusk's capital cost estimates total C$35.6 million across all three phases, with Phase 2 targeting grinding, flotation, and concentrate dewatering at C$12.6 million, and Phase 3 targeting full concentrate production capability at C$21.2 million. The release also identifies approximately C$8.0 million in fuel and air transportation costs associated with the overall program, bringing the total indicative program cost to approximately C$43.7 million. All estimates include a 15% contingency but exclude certain supporting infrastructure such as underground mine development and water treatment. Tusk's preliminary schedule targets July 2028 for full concentrate production readiness at 1,000 tpd.