Sierra Madre Gold and Silver Ltd. (TSXV: SM) (OTCQX: SMDRF) reported record quarterly mill throughput and silver production for the three months ended September 30, 2026, with silver output rising 39% quarter-over-quarter to 89,145 ounces. Net revenues climbed 45% year-over-year to US$8.58 million, while gross profit reached US$1.54 million. The company also confirmed that its Phase 1 expansion throughput goal of 750–800 tonnes per day at La Guitarra was achieved following the quarter's close, a milestone investors had been tracking closely.
Key Points
- Sierra Madre Gold and Silver Ltd. (TSXV: SM) (OTCQX: SMDRF)
- Record Q3 2026 mill throughput of 50,795 tonnes and silver production of 89,145 ounces, both up sharply from Q2 2026
- Net revenues of US$8.58 million; cash costs improved by US$7.55 per silver-equivalent ounce versus Q2 2026; cash and equivalents of US$18.5 million at September 30, 2026
- Investors may be watching commissioning of the new ball mill expected in late November 2026 and Phase 2 expansion progress targeting Q3 2027 completion
Record La Guitarra Production Drives Q3 2026 Revenue Gains
Sierra Madre's La Guitarra mine complex posted record performance in Q3 2026, with 50,795 tonnes milled — up 22% from Q2 2026 — and silver-equivalent production of 159,141 ounces, a 16% quarterly increase. Silver revenues totalled US$5.4 million at US$63.21 per ounce, while gold revenues reached US$3.7 million at US$4,260 per ounce. The company recorded a net loss of US$3.6 million for the quarter, driven primarily by US$2.57 million in non-cash share-based compensation related to stock option vesting, as well as higher investor relations and head office costs following the Del Toro acquisition.
Phase 1 Throughput Milestone Confirmed and Ball Mill Installation Advances
Following the quarter's end, mill throughput at La Guitarra averaged 751 tonnes per day in October 2026, meeting the Phase 1 expansion target of 750–800 tpd and representing a 50% increase over the prior nameplate capacity of 500 tpd. Installation of the new 11x12.5 ball mill has been completed, with drive motor, cyclones, and instrumentation work underway. The company states that commissioning and testing are expected to begin in late November 2026. Combined with existing mills, the new equipment is anticipated to support the Phase 2 milling capacity target of 1,200–1,500 tpd.
Cost Improvements and Fresh Mineralization Underpin Operational Progress
Cash costs of US$41.73 per silver-equivalent ounce produced improved by US$7.55 from Q2 2026, supported by higher throughput, improved silver recoveries, and a greater share of fresh mineralized material reaching the mill. The company disclosed that fresh mineralized tonnes mined have increased threefold since the accelerated development program began across its three mines. Cash and cash equivalents stood at US$18.5 million at September 30, 2026, with working capital of US$23.0 million. The company also confirmed full repayment of a US$5 million secured term loan with First Majestic Silver.
East District Drill Program and Del Toro Mapping Add Exploration Dimension
Beyond operations, Sierra Madre launched a 30,000-metre drill program in the East District of the Guitarra mine complex, with a rig on site since October 29, 2026, targeting the Magdalena and Los Locos vein systems. First assay results are expected in Q1 2027. At the Del Toro silver mine, a 1:2,000 scale geologic mapping and sampling program is underway, with initial reconnaissance identifying silver, zinc, lead, and copper mineralization. Drilling at Del Toro is expected to begin in mid-2027, according to the company's disclosure.